Theory before task 4 · 9 min

The subcontractor list on a California public bid

Carry the number and list your subs

After this lecture you can

  1. Carry an award into the base bid.
  2. Work out the listing threshold from the total bid.
  3. Decide which subcontractors the bid form must name.
1 / 4

Why the law asks for names

California's Subletting and Subcontracting Fair Practices Act makes a prime bidder on public work name, in its bid, each subcontractor whose work is above one-half of 1 percent of the prime's total bid, with the portion of the work each will do. The aim is to stop bid shopping: once a sub is named, the prime cannot squeeze its price after winning by threatening to swap it.

Example. On this job the list goes in the sealed envelope at 2:00 pm.
2 / 4

The threshold is on the total bid

The base is the prime contractor's total bid: every trade, general conditions, fee and bond. Take one-half of 1 percent of it, then name every sub whose portion is above that figure. Your own forces are not listed. A portion with no sub named is one you have agreed to do yourself.

Example. A smaller school bid: the threshold moves with the total.
Total bid, fee and bond included$4,280,000.00
Threshold: one-half of 1 percent$21,400.00
3 / 4

After the bid

A listed sub can be replaced only on the grounds Public Contract Code 4107 sets out, such as refusing to sign the subcontract or failing to perform, and only with the awarding authority's consent. A cheaper offer after the bid is not one of them.

Example. The list is a commitment to the subs as well as to the district.
Common mistake

The threshold on direct cost

The estimator takes the threshold from the cost before markups, because that is the figure on screen while the trades are being carried. The base is lower, the threshold is lower, and a sub just under the real threshold gets named when it need not be, or the count is wrong. Use the Grand Total, the figure that goes on the bid form.

Example. Fee and bond are part of the total bid.

A smaller bid

A different school bid by the same GC.

Not to scale
The problem
  • Total bid $4,280,000, fee and bond included.
  • Sealants sub $24,800; signage sub $19,900.
Step 1 of 2

Threshold

What is the listing threshold?

$4,280,000 × 0.005 = $21,400.00.

Step 2 of 2

Sealants

By how much is the sealants sub above the threshold?

$24,800 − $21,400.00 = $3,400.00: listed. Signage is below: not required.

In short. Threshold on the total bid; name every sub above it; own forces never.

Check yourself

Question 1 of 2

Which figure is the base for the listing threshold?

  • Right.

  • The rule says the total bid.

  • The base is the prime's bid.

  • The bid, not the budget.

Question 2 of 2

A total bid is 6,350,000. What is the listing threshold?

6,350,000 × 0.005 = 31,750.