Course introduction · 3 min

Interim payment under FIDIC: retention, IPC, late payment

You are the main contractor's quantity surveyor on a six-storey mixed-use building. It is the end of month 11 under the FIDIC Red Book, and retention is about to reach its limit. In five tasks you take Statement 11 from the work on site to the money in the bank.

Start task 1

A concrete frame building under construction with a tower crane; no signage.Fictional project
Mixed-use building, 6 storeysMonth 11 · Statement 11 for March
Building
Shops on the ground floor, offices on level 1, flats on levels 2 to 5; concrete frame
Stage
Month 11 of 18: frame complete, envelope and internal walls under way
Contract
FIDIC Red Book 2017, remeasured; retention 10 % up to a limit; US dollars; taxes left out
Work in the ERP
5 tasks, about 1 h 25 min

Who hands what to whom

Every arrow is a figure that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • The EngineerAgrees progress, certifies
    • Agreed progressTask 2
    • Payment CertificateTask 5
YouContractor's quantity surveyor

Goes from you

    • Statement 11Task 4
    • Financing chargesTask 5
    The clientPays the certificate

The project and the people are fictional. Portraits are generated.

Your route through the job

One Statement, in the order a QS builds it. All tasks are free; each happens in the Contracts module.

  1. Limit

    Task 1 · 10 min

    Retention stops at the limit: the room left

    You produce
    Retention room left
    Document
    Contract Data
    In the ERP
    Contracts
  2. Item (i)

    Task 2 · 20 min

    Statement 11: value the work to date, then March

    You produce
    Work to date and March
    Document
    Statement 11
    In the ERP
    Contracts
  3. Item (i)

    Task 3 · 15 min

    Variation 01 in the Statement, at its share

    You produce
    Variation 01 to date
    Document
    Statement 11
    In the ERP
    Contracts
  4. Payment

    Task 4 · 20 min

    Statement 11: retention at the limit, the amount due

    You produce
    Amount due
    Document
    Statement 11
    In the ERP
    Contracts
  5. Payment

    Task 5 · 20 min

    The payment clock, and charges for paying late

    You produce
    Financing charges
    Document
    Statement 12
    In the ERP
    Contracts

How a month of work becomes a payment

Each step below is one task, in the order the Statement is built.

Room
Task 1LimitHow much may still be held.
Item (i)
Task 2Work to dateEvery line at its percent.
V01Item (i)
Task 3VariationIts share built.
Due
Task 4Amount dueLess retention and earlier certificates.
ChargesDue
Task 5Late paymentCharges by the day.

Blue is what the task adds; grey is carried over from before.

In short. Value everything to date, stop retention at its limit, deduct what was certified, and count the clock from the Statement.