Interim payment under FIDIC: retention, IPC, late payment
You are the main contractor's quantity surveyor on a six-storey mixed-use building. It is the end of month 11 under the FIDIC Red Book, and retention is about to reach its limit. In five tasks you take Statement 11 from the work on site to the money in the bank.
Fictional project- Building
- Shops on the ground floor, offices on level 1, flats on levels 2 to 5; concrete frame
- Stage
- Month 11 of 18: frame complete, envelope and internal walls under way
- Contract
- FIDIC Red Book 2017, remeasured; retention 10 % up to a limit; US dollars; taxes left out
- Work in the ERP
- 5 tasks, about 1 h 25 min
Who hands what to whom
Every arrow is a figure that reaches your desk or leaves it, and the task where that happens.
Comes to you
- The EngineerAgrees progress, certifies
- Agreed progressTask 2
- Payment CertificateTask 5
YouContractor's quantity surveyorGoes from you
- Statement 11Task 4
- Financing chargesTask 5
The project and the people are fictional. Portraits are generated.
Your route through the job
One Statement, in the order a QS builds it. All tasks are free; each happens in the Contracts module.
Limit
Task 1 · 10 min
Retention stops at the limit: the room left
- You produce
- Retention room left
- Document
- Contract Data
- In the ERP
- Contracts
Item (i)
Task 2 · 20 min
Statement 11: value the work to date, then March
- You produce
- Work to date and March
- Document
- Statement 11
- In the ERP
- Contracts
Item (i)
Task 3 · 15 min
Variation 01 in the Statement, at its share
- You produce
- Variation 01 to date
- Document
- Statement 11
- In the ERP
- Contracts
Payment
Task 4 · 20 min
Statement 11: retention at the limit, the amount due
- You produce
- Amount due
- Document
- Statement 11
- In the ERP
- Contracts
Payment
Task 5 · 20 min
The payment clock, and charges for paying late
- You produce
- Financing charges
- Document
- Statement 12
- In the ERP
- Contracts
How a month of work becomes a payment
Each step below is one task, in the order the Statement is built.
Blue is what the task adds; grey is carried over from before.
In short. Value everything to date, stop retention at its limit, deduct what was certified, and count the clock from the Statement.