Theory before task 1 · 6 min

Retention and its limit

Retention stops at the limit: the room left

Course introduction

After this lecture you can

  1. Say what retention is for and where its rate and limit are stated.
  2. Work out the limit from the Accepted Contract Amount.
  3. Find the room left before a Statement.
1 / 3

Money held as security

Each Statement keeps back a share of the work valued, the retention, as the Client's security that defects will be put right. The Contract Data states the rate and a limit. Once the amount retained reaches the limit, nothing more is held; half comes back at taking-over and half after the Defects Notification Period.

Example. A contract of 8,000,000 with 10 % retention and a limit of 5 %: retention stops once 400,000 is held.
USD372,000
  • Held so far USD372,000
  • Room left USD28,000
2 / 3

The limit is fixed at award

The limit is a share of the Accepted Contract Amount, the figure in the Letter of Acceptance. Variations change what is paid each month, but the limit stays where the Contract Data put it. Some contracts word it differently; the common FIDIC case is a share of the accepted amount.

Example. After variations of 300,000 the same contract still has a limit of 400,000.
Common mistake

The limit of the varied contract

The contract record in the ERP shows the current value, variations included. Taking 5 % of that raises the limit and lets the Client hold more than the Contract allows.

Example. 5 % of 8,300,000 is 415,000: 15,000 held that the Contract does not allow.

Room left on a smaller contract

Different numbers from your task.

Not to scale
The problem
  • Accepted Contract Amount USD8,000,000; limit 5 %.
  • Retention held after the last certificate USD372,000.
Step 1 of 2

Limit

Limit of Retention Money?

USD8,000,000 x 5 % = USD400,000.

Step 2 of 2

Room left

Room left before the next Statement?

USD400,000 - USD372,000 = USD28,000.

In short. Limit from the accepted amount; room left = limit less retention held.

Check yourself

Question 1 of 3

The limit of Retention Money is a share of:

  • Right.

  • Variations do not move it.

  • That is what the rate applies to.

Question 2 of 3

Retention held has reached the limit. The next Statement holds:

  • Right.

  • The deduction stops at the limit.

  • There is no lower rate.

Question 3 of 3

Accepted amount 6,000,000, limit 5 %, held 288,000. Room left?

6,000,000 x 5 % = 300,000; less 288,000 = 12,000.

Read the source