Money held as security
Each Statement keeps back a share of the work valued, the retention, as the Client's security that defects will be put right. The Contract Data states the rate and a limit. Once the amount retained reaches the limit, nothing more is held; half comes back at taking-over and half after the Defects Notification Period.
- Held so far USD372,000
- Room left USD28,000