What the Statement lists
After each month the Contractor sends the Engineer a Statement. It starts with the value of the work executed up to the end of the month, then adds or deducts the other items the Contract allows: adjustments, retention, an advance and its repayment, plant and materials on site, and finally the amounts of all earlier Payment Certificates.
- Certified before USD1,500,000
- This month USD400,000