Theory before task 2 · 7 min

The Statement is cumulative

Statement 11: value the work to date, then March

After this lecture you can

  1. List what a FIDIC Statement contains.
  2. Value work to date from agreed progress.
  3. Find a month's work by difference.
1 / 3

What the Statement lists

After each month the Contractor sends the Engineer a Statement. It starts with the value of the work executed up to the end of the month, then adds or deducts the other items the Contract allows: adjustments, retention, an advance and its repayment, plant and materials on site, and finally the amounts of all earlier Payment Certificates.

Example. Work to date 1,900,000; earlier certificates 1,500,000 net: the Statement asks for the difference, less retention.
USD1,500,000USD400,000
  • Certified before USD1,500,000
  • This month USD400,000
2 / 3

Agreed progress, line by line

Each line of the Schedule is valued at its share complete, agreed with the Engineer. A time-related line earns as time passes; a provisional sum earns only what the Engineer instructed.

Example. A line of 500,000 that is 40 % complete is worth 200,000 to date.
Common mistake

Valuing the month

Valuing only what was done this month looks simpler. Then any line missed last month is never caught up. Value everything to date and let the earlier certificates take off what was paid.

Example. A line forgotten in month 4 comes back in month 5 automatically when work is valued to date.

A month by difference

Different numbers from your task.

Not to scale
The problem
  • Line A USD500,000, 40 % to date; line B USD300,000, complete.
  • Last Statement's work to date USD180,000.
Step 1 of 2

Work to date

Work executed to date?

USD500,000 x 40 % + USD300,000 = USD500,000.

Step 2 of 2

This month

Work executed this month?

USD500,000 - USD180,000 = USD320,000.

In short. Value to date, then the month falls out by difference.

Check yourself

Question 1 of 3

Item (i) of the Statement values the work:

  • Right.

  • It is cumulative.

  • Payment dates do not set it.

Question 2 of 3

A time-related preliminaries line earns:

  • Right.

  • That is the fixed part.

  • It earns every month.

Question 3 of 3

Work to date 2,150,000; last Statement's work to date 1,870,000. Work this month?

2,150,000 - 1,870,000 = 280,000.