All 5 tasks freeIntermediate1.5 h of studyInternational
Interim payment under FIDIC: retention, IPC, late payment
On a fictional six-storey mixed-use building in its eleventh month.
Who it's for Contractor's quantity surveyor

You will be able to
Skills checked
- Find the retention room left under a FIDIC limit of Retention Money
- Value the work executed to date in a cumulative Statement and find the month by difference
- Value an agreed variation at its share executed
- Work out the amount due after retention at its limit and earlier certificates
- Count the FIDIC payment clock and work out financing charges on a late payment
Tasks
A task as it opens in the trainer, before you enter anything.

- 1
- 2
- 3
- 4
- 5The payment clock, and charges for paying lateFoundation≈20 minTheory · 7 minCheat sheet: every rule on one page
Difficulty is calculated from the steps and the figures you check in each task. Time is the median of real learners once enough have finished; until then it is the author's estimate.
Certificate
Awarded when all 5 tasks pass the numbers, trace and explain checks.

Files you work with
Created in your OpenConstructionERP workspace the moment you enrol.
- parties3 records
- Billingcontract
- Billingprogress records7 lines
What next
Questions about this course? Write to info@datadrivenconstruction.io
Related courses

Your roleContractor's quantity surveyor
Price, win and vary a FIDIC contract
Take one building from tender to its first variation under the FIDIC Red Book 2017: price the last blank lines, build the tender sum, level and award the drywall.
Foundation1.5 h of studyFigures checked 21EN
All 5 tasks freeCertificate of completion
Your roleSite surveyorLand parcels: boundary, area, overlap, split and register
On a fictional development plot of about 2.4 ha.
Intermediate2 h of studyFigures checked 10EN
All 5 tasks freeCertificate of completion
Your roleQuality manager of the main contractorQuality control: hold point, NCR, RFI to taking-over
On a fictional six-storey mixed-use building under a FIDIC Red Book contract.
Intermediate1.5 h of studyFigures checked 9EN
All 5 tasks freeCertificate of completion