Cheat sheet

Interim payment under FIDIC: retention, IPC, late payment

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Retention stops at the limit: the room left

Theory (6 min)
Rule
Retention stops at the limit. The limit is a share of the Accepted Contract Amount, whatever the variations do.
How it is built
  • Room left = Accepted Contract Amount × 5 % − Held after IPC 10
Usual mistake
You took 5 % of the current contract value. The limit is on the Accepted Contract Amount; Variation 01 does not move it.
At work
Before each Statement the QS checks retention held against the limit in the Contract Data.

Task 2

Statement 11: value the work to date, then March

Theory (7 min)
Rule
A Statement is cumulative. Item (i) values everything executed to the end of the month.
How it is built
  • Work in March = Claim gross − Statement 10, item (i)
Usual mistake
That is the work to date, the claim gross. Take off item (i) of Statement 10 to see March alone.
At work
At month end the QS agrees progress with the Engineer and values every line to date.

Task 3

Variation 01 in the Statement, at its share

Theory (6 min)
Rule
Pay what is built, at the agreed value. The agreed value already carries the rate of the Contract.
How it is built
  • Variation 01 to date = Agreed value × m2 built ÷ m2 instructed
Usual mistake
That is the whole variation. Only 105 of the 140 m2 are built; value the share built.
At work
The QS adds each agreed variation to the Statement as it is executed, at its share.

Task 4

Statement 11: retention at the limit, the amount due

Theory (7 min)
Rule
Retention to date never passes the limit, and every earlier certificate comes off item (i).
How it is built
  • Amount due = Item (i) − Retention at the limit − IPC 1 to 10
Usual mistake
You held 10 % of everything to date. Retention stops at the limit: this month only the room left comes off.
At work
The QS builds the Statement from item (i) down, deduction by deduction, and checks each against the Contract.

Task 5

The payment clock, and charges for paying late

Theory (7 min)
Rule
The 56 days run from the Statement. Every day after them earns financing charges, without notice.
How it is built
  • Financing charges = Amount due × Yearly rate × Days late ÷ 365
Usual mistake
You counted from the latest certificate date. Payment is late only after the 56 days of 14.7.
At work
The QS tracks both clocks for every Statement and adds any charges to the next one.