Cheat sheet
Interim payment under FIDIC: retention, IPC, late payment
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- Retention stops at the limit. The limit is a share of the Accepted Contract Amount, whatever the variations do.
- How it is built
- Room left = Accepted Contract Amount × 5 % − Held after IPC 10
- Usual mistake
- You took 5 % of the current contract value. The limit is on the Accepted Contract Amount; Variation 01 does not move it.
- At work
- Before each Statement the QS checks retention held against the limit in the Contract Data.
- Rule
- A Statement is cumulative. Item (i) values everything executed to the end of the month.
- How it is built
- Work in March = Claim gross − Statement 10, item (i)
- Usual mistake
- That is the work to date, the claim gross. Take off item (i) of Statement 10 to see March alone.
- At work
- At month end the QS agrees progress with the Engineer and values every line to date.
- Rule
- Pay what is built, at the agreed value. The agreed value already carries the rate of the Contract.
- How it is built
- Variation 01 to date = Agreed value × m2 built ÷ m2 instructed
- Usual mistake
- That is the whole variation. Only 105 of the 140 m2 are built; value the share built.
- At work
- The QS adds each agreed variation to the Statement as it is executed, at its share.
- Rule
- Retention to date never passes the limit, and every earlier certificate comes off item (i).
- How it is built
- Amount due = Item (i) − Retention at the limit − IPC 1 to 10
- Usual mistake
- You held 10 % of everything to date. Retention stops at the limit: this month only the room left comes off.
- At work
- The QS builds the Statement from item (i) down, deduction by deduction, and checks each against the Contract.
- Rule
- The 56 days run from the Statement. Every day after them earns financing charges, without notice.
- How it is built
- Financing charges = Amount due × Yearly rate × Days late ÷ 365
- Usual mistake
- You counted from the latest certificate date. Payment is late only after the 56 days of 14.7.
- At work
- The QS tracks both clocks for every Statement and adds any charges to the next one.