OpenConstruction Academy
Sign in / Register
EN

Theory before task 5 · 7 min

The payment clock and financing charges

The payment clock, and charges for paying late

After this lecture you can

  1. Find the latest dates for the certificate and the payment.
  2. Count the days late.
  3. Work out financing charges.
1 / 3

Two clocks from one day

Both periods start when the Engineer receives the Statement: 28 days to issue the Interim Payment Certificate, 56 days for the Client to pay. A late certificate does not move the payment date.

Example. Statement received 3 March: certificate by 31 March, payment by 28 April.
2 / 3

Financing charges

If payment is late, the Contractor is owed financing charges on the amount unpaid, from the date payment was due, compounded monthly, at 3 percentage points a year above the average bank short-term lending rate to prime borrowers, unless the Contract Data states another rate. No notice or certificate is needed. If payment stays late, the Contractor may give notice and suspend or slow the work. Practice on the rate differs by country; the Contract Data states it.

Example. 400,000 paid 15 days late at 8 % a year, under a month so nothing compounds yet: 400,000 x 8 % x 15 / 365 = 1,315.07.
USD400,000
  • Due USD400,000
  • Charges USD1,315
Common mistake

Counting from the certificate

The certificate's deadline is earlier than the payment's. Counting the delay from it adds four weeks that were never late, and the Engineer will strike the claim out.

Example. Counting from 31 March instead of 28 April turns 15 days late into 43.

Charges on a smaller payment

Different numbers from your task.

Not to scale
The problem
  • Amount certified USD400,000, paid 15 days after the date for payment.
  • Rate 8 % a year, 365-day year.
Step 1 of 1

Charges

Financing charges?

USD400,000 x 8 % x 15 / 365 = USD1,315.07.

In short. Days late from the payment date, then amount x rate x days / 365.

Check yourself

Question 1 of 3

The 56 days for payment run from:

  • Right.

  • The clock starts at the Statement.

  • It starts on receipt.

Question 2 of 3

To be owed financing charges the Contractor needs:

  • Right.

  • Not under 14.8.

  • Not for the charges.

Question 3 of 3

250,000 paid 10 days late at 7.3 % a year (365 days). Charges?

250,000 x 7.3 % x 10 / 365 = 500.00.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.