Two clocks from one day
Both periods start when the Engineer receives the Statement: 28 days to issue the Interim Payment Certificate, 56 days for the Client to pay. A late certificate does not move the payment date.
Theory before task 5 · 7 min
The payment clock, and charges for paying late
Both periods start when the Engineer receives the Statement: 28 days to issue the Interim Payment Certificate, 56 days for the Client to pay. A late certificate does not move the payment date.
If payment is late, the Contractor is owed financing charges on the amount unpaid, from the date payment was due, compounded monthly, at 3 percentage points a year above the average bank short-term lending rate to prime borrowers, unless the Contract Data states another rate. No notice or certificate is needed. If payment stays late, the Contractor may give notice and suspend or slow the work. Practice on the rate differs by country; the Contract Data states it.
The certificate's deadline is earlier than the payment's. Counting the delay from it adds four weeks that were never late, and the Engineer will strike the claim out.
Different numbers from your task.
Financing charges?
Hint: Amount x rate x days / 365.
Right.
The clock starts at the Statement.
It starts on receipt.
Right.
Not under 14.8.
Not for the charges.
Free official texts. The lecture cites clause numbers and puts the rules in its own words.
The 28 days for the certificate and the 56 days for the payment, both from the Statement.
Financing charges on a late payment: the rate, compounding, and that no notice is needed.
What the Contractor may do if payment stays late: notice, then suspension or a reduced rate of work.