Deductions from the top
The amount due is built down from the work to date: less retention to date, never above the limit, less every earlier Payment Certificate. Where there is an Advance Payment, its repayment comes off too; this Contract has none.
- 1 Work to date
- 2 Retention
- 3 Earlier certificates
- 4 Amount due