Theory before task 4 · 7 min

From item (i) to the amount due

Statement 11: retention at the limit, the amount due

After this lecture you can

  1. Deduct retention to date, capped at the limit.
  2. Deduct the earlier certificates.
  3. Explain why an ERP's net figure may differ.
1 / 3

Deductions from the top

The amount due is built down from the work to date: less retention to date, never above the limit, less every earlier Payment Certificate. Where there is an Advance Payment, its repayment comes off too; this Contract has none.

Example. Work to date 3,000,000; retention at its limit of 140,000; earlier certificates 2,600,000.
+USD3,000,0001−USD140,0002−USD2,600,0003USD260,0004
  • 1 Work to date
  • 2 Retention
  • 3 Earlier certificates
  • 4 Amount due
2 / 3

The month the limit is reached

In that month the retention deducted is only the room left. The month's work is paid almost in full, which is the cash-flow turn a contractor waits for.

Example. Room left 6,000 on a month of 260,000: the Statement holds 6,000, not 26,000.
Common mistake

Copying the software's net figure

A claim screen may show its own net due: the claim less a flat retention, with no knowledge of certificates issued outside it. Build the amount due from the Contract and check the screen against it, not the other way.

Example. A net due of 2,700,000 against an amount due of 260,000 is a sign that earlier certificates are missing.

Amount due in the limit month

Different numbers from your task.

Not to scale
The problem
  • Work to date USD3,000,000; limit of retention USD140,000, reached this month.
  • Earlier certificates USD2,600,000.
Step 1 of 1

Amount due

Amount due?

USD3,000,000 - USD140,000 - USD2,600,000 = USD260,000.

In short. Retention to date at most the limit; earlier certificates off.

Check yourself

Question 1 of 3

Retention to date in a Statement is:

  • Right.

  • Not above the limit.

  • It is a figure to date.

Question 2 of 3

The earlier certificates deducted are:

  • Right.

  • Their retention was not paid.

  • All of them.

Question 3 of 3

Work to date 1,200,000, retention limit 50,000 reached, earlier certificates 1,050,000. Amount due?

1,200,000 - 50,000 - 1,050,000 = 100,000.