All 5 tasks freeIntermediate1.5 h of studyInternational
Quality control: hold point, NCR, RFI to taking-over
On a fictional six-storey mixed-use building under a FIDIC Red Book contract.
Who it's for Quality manager of the main contractor

You will be able to
Skills checked
- Stand down a pour at a failed hold point and work out the concrete held (FIDIC 7.3)
- Raise an NCR with a root cause you can change and price the rework (ISO 9001 10.2, FIDIC 7.5)
- Set an RFI's due date in working days and value the Engineer's answer as a Variation (FIDIC 13.3.1)
- Sort a punch list into what holds taking-over and what goes to the defects period (FIDIC 10.1)
- Assemble the quality records for taking-over and report how complete the package is (ISO 9001 7.5)
Tasks
A task as it opens in the trainer, before you enter anything.

- 1
- 2
- 3
- 4
- 5The quality records for taking-overFoundation≈20 minTheory · 8 minCheat sheet: every rule on one page
Difficulty is calculated from the steps and the figures you check in each task. Time is the median of real learners once enough have finished; until then it is the author's estimate.
Certificate
Awarded when all 5 tasks pass the numbers, trace and explain checks.

What next
Questions about this course? Write to info@datadrivenconstruction.io
Related courses
Your roleSite surveyorLand parcels: boundary, area, overlap, split and register
On a fictional development plot of about 2.4 ha.
Intermediate2 h of studyFigures checked 10EN
All 5 tasks freeCertificate of completion

Your roleContractor's quantity surveyor
Interim payment under FIDIC: retention, IPC, late payment
On a fictional six-storey mixed-use building in its eleventh month.
Intermediate1.5 h of studyFigures checked 11EN
All 5 tasks freeCertificate of completion
Your roleLand surveyor on the development plotSite levels: platform, cut and fill, building corners
On a fictional 2.4 ha development plot.
Intermediate2 h of studyFigures checked 16EN
All 5 tasks freeCertificate of completion