Evidence, not paper
ISO 9001 7.5 asks for documented information to be kept as evidence that the work conforms. On a building that means the inspection and test records with their hold-point releases, the NCRs with their closures, and the test certificates the contract names (FIDIC 7.4). They go to the Engineer with the as-built records before taking-over.