Theory before task 5 · 8 min

Close-out: the records that prove the quality

The quality records for taking-over

After this lecture you can

  1. Say what quality records a handover package holds.
  2. Tell a delivered document from a verified one.
  3. Work out the completeness of a package.
1 / 3

Evidence, not paper

ISO 9001 7.5 asks for documented information to be kept as evidence that the work conforms. On a building that means the inspection and test records with their hold-point releases, the NCRs with their closures, and the test certificates the contract names (FIDIC 7.4). They go to the Engineer with the as-built records before taking-over.

Example. An NCR closed without a re-inspection record is a claim, not evidence.
2 / 3

Delivered is not verified

A document can be missing, delivered (bound to its slot) or verified (checked and signed off). Only verified evidence counts. A package also holds slots the ERP makes when it is built, such as the punch list closure: they count only after the build, and only when the work behind them is closed.

Example. Twelve required slots with seven verified stand at 58 %.
$7$3$2
  • Verified $7
  • Delivered, not checked $3
  • Missing or generated $2
Common mistake

Counting what is bound

A package where every slot has a file looks finished. If nobody has checked the files, the Engineer will find the wrong revision of the manual at the worst moment. Count verified slots only.

Example. Check the evidence in the slot, then tick verified.

Completeness of a package

Different numbers from your task.

Not to scale
The problem
  • 12 required slots, including three the build makes.
  • 7 verified; three more bound but not checked.
Step 1 of 1

Completeness

Completeness, per cent (rounded)?

7 ÷ 12 × 100 = 58 %.

In short. Verified over required, the generated slots included.

Check yourself

Question 1 of 3

A slot holds a file that nobody has checked. It is...

  • Right.

  • Verified needs a check.

  • Binding does not remove a requirement.

Question 2 of 3

Why add the inspection and test records as a slot of their own?

  • Right. ISO 9001 7.5 and FIDIC 4.9.

  • As-built drawings have their own slot.

  • An added required slot can only lower it until verified.

Question 3 of 3

16 required slots, 9 verified. Completeness, per cent, rounded?

9 ÷ 16 × 100 = 56 %.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.