Theory before task 4 · 8 min

Punch list to taking-over

Punch list before taking-over

After this lecture you can

  1. Run a snag from open to closed and keep the record.
  2. Tell what must be fixed before taking-over from what may be listed (FIDIC 10.1, 11.1).
  3. Total the rework that holds taking-over.
1 / 3

A snag has a life

A snag found on a walk-round is entered with its location, trade, priority and an estimate of the rework. It is started, marked resolved by the trade, verified by the person who found it, and closed. Closed snags stay on the list: they are the record of what was found and fixed.

Example. A snag that is marked resolved but never verified is still open in everyone's eyes but the trade's.
2 / 3

Taking-over with a list

Under FIDIC 10.1 the Engineer may issue the Taking-Over Certificate with minor outstanding work and defects listed, as long as they do not substantially affect the safe use of the works. The contractor finishes them in the Defects Notification Period (11.1). Safety items and anything that lets water in are fixed first.

Example. A missing window handle can be listed; a fire door that does not close cannot.
Before taking-over
$2
Listed on the certificate
$5
Closed
$3
Common mistake

Waiting for a zero list

A contractor who waits until every snag is closed hands over late and pays site costs for weeks over paint touch-ups. The opposite mistake is to treat a safety item as a snag. Sort by consequence first, then fix.

Example. Ask of each snag: does it stop safe use or let water in? Only those hold taking-over.

What holds taking-over

Different numbers from your task.

Not to scale
The problem
  • Open snags: smoke detector missing ($220, critical); gutter joint leaking ($140, high).
  • Door stop missing ($70, low); skirting scuffed ($25, low).
Step 1 of 1

Before taking-over

Rework that holds taking-over?

$220 + $140 = $360.

In short. Safety and water before taking-over; the rest listed and done in the defects period.

Check yourself

Question 1 of 3

A snag is marked resolved by the trade. Is it closed?

  • Right. The finder checks the fix.

  • Resolved is the trade's claim.

  • Cost does not close a snag.

Question 2 of 3

A leaking roof outlet is found at the walk-round. It is...

  • Right. Water in the building affects safe use.

  • It lets water in.

  • It is the contractor's defect.

Question 3 of 3

Open snags: critical 300, high 120, medium 55, low 30. Rework before taking-over?

300 + 120 = 420.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.