After this lecture you can

  1. Set an RFI's response due date in working days.
  2. Say what FIDIC 1.9 lets the contractor do when an answer is late.
  3. Value the answer as a Variation on what changes only.
1 / 3

A question with a date

FIDIC does not use the term RFI; the contract's procedure, usually in the Specification, sets how fast the Engineer answers. Count the due date in working days from the day the RFI is raised. Put the date the work needs the answer next to it: the gap between the two is the float the question has.

Example. Raised on a Monday with a five-working-day period, the answer is due the next Monday.
Raised0
Working days allowed5
Due, in working days from raising5
2 / 3

When the answer is late

Under FIDIC 1.9, when the contractor will be delayed by a drawing or instruction not issued in time, it gives the Engineer notice with what is needed and by when. If the delay happens, the contractor may claim time and cost under 20.2, unless the lateness comes from its own error. An RFI log with due dates is the evidence for that notice.

Example. Practice differs by country in the name and the period; the notice and the record are common to all.
Common mistake

Pricing the whole wall

An answer that adds insulation to a partition already in the bill does not make the whole partition new. Studs and boards are paid as measured; the Variation is the insulation. Pricing the full new wall pays the studs and boards twice.

Example. Value what the answer adds, on the walls and levels it covers.

Valuing an RFI answer

Different numbers from your task.

Not to scale
The problem
  • The answer adds insulation to 200 m2 of separating walls on each of 3 levels.
  • The agreed rate is $5.50 a m2.
Step 1 of 2

Area

Wall area changed, m2?

200 × 3 = 600 m2.

Step 2 of 2

Value

Cost impact?

600 × $5.50 = $3,300.00.

In short. Due date in working days; value only what the answer adds.

Check yourself

Question 1 of 3

The answer to an RFI arrives after the date the work needed it. The contractor...

  • Right. FIDIC 1.9 and 20.2 need the notice.

  • A late instruction can carry time and cost.

  • That hides the delay.

Question 2 of 3

An RFI is raised on a Thursday with five working days to answer. It is due...

  • Right. Five working days skip the weekend.

  • That counts calendar days.

  • Count five working days: Friday, Monday, Tuesday, Wednesday, Thursday.

Question 3 of 3

Insulation is added to 150 m2 of separating walls on each of 5 levels at 7.00 a m2. Cost impact?

150 × 5 × 7.00 = 5,250.