Theory before task 1 · 8 min

Hold points: the check that stops the work

A hold point fails the day before a pour

Course introduction

After this lecture you can

  1. Tell a hold point from a witness point in an inspection and test plan.
  2. Say what FIDIC 7.3 asks before work is covered.
  3. Work out the concrete a failed hold point stands down.
1 / 3

The inspection and test plan

An inspection and test plan (ITP) lists each check on a piece of work: what is checked, against what, by whom, and whether the work must stop for it. At a hold point the work does not go on until the check is released in writing. At a witness point the check is offered; if nobody comes at the stated time, the work may go on.

Example. A slab pour: formwork and reinforcement are hold points; delivery tickets and test cubes are witness points.
Formwork
$1
Reinforcement
$1
Delivery tickets
$1
Test cubes
$1
2 / 3

Notice before the work is covered

Under FIDIC 7.3 the contractor gives notice whenever work is ready for inspection before it is covered up. The Engineer then inspects without unreasonable delay, or says that no inspection is needed. Work covered without notice may have to be opened up at the contractor's cost. ISO 9001 8.6 says the same in general terms: release only after the planned checks.

Example. Notice in the morning for an afternoon inspection gives the Engineer the time the ITP allows, and the pour stays possible next day.
Common mistake

Signing the hold point after the pour

When the concrete is already booked, the pressure is to pour and sign later. A hold point signed after the concrete is in records a check that never happened. Stop the pour, record the fail, and stand the delivery down while it still costs a cancellation charge rather than a repair.

Example. Stand down only the bay that failed: the rest of the slab, if released, can go on.

Concrete held on a failed bay

Different numbers from your task.

Not to scale
The problem
  • The failed bay measures 20 m by 18 m, with a lift opening of 20 m2 inside it.
  • The slab is 300 mm thick.
Step 1 of 2

Net area

Net area of the bay, m2?

20 × 18 − 20 = 340 m2.

Step 2 of 2

Volume

Concrete to stand down, m3?

340 × 0.3 = 102 m3.

In short. Only the failed bay is held, and only where concrete would go.

Check yourself

Question 1 of 3

At a witness point nobody comes at the stated time. The work...

  • Right. That is the difference from a hold point.

  • That is a hold point.

  • Nobody asks for that at a witness point.

Question 2 of 3

Work was covered without the notice FIDIC 7.3 asks for. If the Engineer asks, the contractor...

  • Right. Notice is what protects the contractor.

  • The Engineer may ask to see covered work.

  • Not when the notice was missing.

Question 3 of 3

A bay 15 m by 12 m has a 9 m2 opening; the slab is 0.25 m thick. Concrete held, in m3?

(15 × 12 − 9) × 0.25 = 42.75 m3.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.