Course introduction · 3 min

Quality control: hold point, NCR, RFI to taking-over

Mixed-use building, 6 storeys · Quality from the frame to taking-over · Fictional project

You are the main contractor's quality manager on a six-storey mixed-use building under a FIDIC Red Book contract. A slab bay fails its reinforcement check the day before the pour. In five tasks you follow quality the way it runs on site: the hold point, the NCR and what it cost, an RFI answered in time, the snags before taking-over, and the records that prove it all.

Start task 1

Job
Mixed-use building, 6 storeys, frame to taking-over
Contract
FIDIC Red Book 2017, remeasurement, US dollars
Method
Inspection and test plan, NCRs and corrective action after ISO 9001
Work in the ERP
5 tasks, about 1 h 30 min

Who hands what to whom

Every arrow is something that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • Concrete frame subcontractorFixes the reinforcement
    • Notice for the hold pointTask 1
  • Drywall subcontractorBuilds the partitions
    • A questionTask 3
YouQuality manager

Goes from you

    • NCR-001Task 2
    • Snag listTask 4
    • Records packageTask 5
    The EngineerInspects, answers, takes over

Your route through the job

One quality record, built in the order it happens on site. Every task is free.

  1. Inspect

    Task 1 · 10 min

    A hold point fails the day before a pour

    You produce
    Concrete stood down
    Document
    Inspection record
    In the ERP
    Inspections
  2. Inspect

    Task 2 · 20 min

    NCR-001: root cause and the cost of rework

    You produce
    Cost of the nonconformity
    Document
    NCR
    In the ERP
    Non-conformance
  3. Ask

    Task 3 · 20 min

    An RFI answered in time, and its cost

    You produce
    Due date and value of an answer
    Document
    RFI log
    In the ERP
    RFI
  4. Hand over

    Task 4 · 20 min

    Punch list before taking-over

    You produce
    Rework before taking-over
    Document
    Punch list
    In the ERP
    Punch List
  5. Hand over

    Task 5 · 20 min

    The quality records for taking-over

    You produce
    Completeness of the records
    Document
    Close-out package
    In the ERP
    Close-out

How quality is proved, not just done

Each step below is one task, in the order it happens.

HeldReleased
Task 1Hold pointNo release, no pour.
TimeRepair
Task 2NCRThe cause and the full cost.
VariationIn time
Task 3RFIA date, then a price.
ListedBefore
Task 4SnagsSafety first; the rest listed.
WaitingVerified
Task 5RecordsVerified evidence only.

Blue is what the task adds; grey is carried over from before.

In short. Check before the work hides it, price the whole failure, answer on time, hand over what is safe, and keep the evidence.