Cheat sheet

Quality control: hold point, NCR, RFI to taking-over

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

A hold point fails the day before a pour

Theory (8 min)
Rule
A hold point is released before the work hides it. No release, no pour: the concrete is stood down.
How it is built
  • Concrete stood down = Bay B area − Core opening × Slab thickness
Usual mistake
The core opening is in. No concrete goes into it; deduct it from the bay.
At work
The quality manager records the fail at once and the site manager calls the plant before the cut-off.

Task 2

NCR-001: root cause and the cost of rework

Theory (9 min)
Rule
A nonconformity costs the repair, the time the site waits, and the client's repeat check. All of it goes on the NCR.
How it is built
  • NCR-001 cost impact = Rework + Concrete cancelled + Pump cancelled + Site overheads × days + Repeat inspection
Usual mistake
The site overheads are missing. The frame is critical, so every working day the pour moved cost the site.
At work
The NCR goes into the monthly quality report with its cost and the corrective action for the next pour.

Task 3

An RFI answered in time, and its cost

Theory (8 min)
Rule
An RFI carries a date and its answer carries a price. The change is valued on what it adds.
How it is built
  • RFI-001 cost impact = Separating walls per level × Flat levels × Insulation rate
Usual mistake
Walls inside a flat are in. The answer covers walls between flats and to the corridor.
At work
The quality manager keeps the RFI log; the quantity surveyor values the answer as a Variation.

Task 4

Punch list before taking-over

Theory (8 min)
Rule
Taking-over waits for safe use, not for a zero list. Safety and water first; the rest is listed.
How it is built
  • Rework before taking-over = Critical snags + High snags
Usual mistake
All open items are in. Low and medium ones go on the certificate's list.
At work
The Engineer and the contractor walk the building together and agree the list before the application.

Task 5

The quality records for taking-over

Theory (8 min)
Rule
Delivered means verified. A file nobody has checked is not yet evidence of quality.
How it is built
  • Completeness = Verified slots ÷ Required slots
Usual mistake
Bound but unverified documents are counted. Only verified evidence counts.
At work
The quality manager binds and checks the records; the Engineer reviews the package with the taking-over application.