Course introduction · 3 min
Office fit-out: measure, price and budget with GST (India)
You are the fit-out estimator at the project management consultant of a software company taking a new floor. The tender BOQ goes out on Friday and the CFO signs the budget on Monday. In four tasks you measure the carpet, take the partitions off the drawing, test the bill against the board's cost per sq ft, and add the GST the tenant will not get back.
Fictional project- Works
- Partitions, ceilings, floor finishes, joinery and services on one leased floor
- Contract
- Item-rate tender BOQ; works contract under GST
- Method
- IS 1200 measurement, PDF takeoff, cost per sq ft of carpet area
- Work in the ERP
- 4 tasks, about 57 min
Who hands what to whom
Every arrow is a figure that reaches your desk or leaves it, and the task where that happens.
Comes to you
- DesignerSheet A-101
- DrawingTask 2
- LandlordThe lease
- AreasTask 3
YouFit-out estimator, PMCGoes from you
- Tender BOQTask 1
- Cost per sq ftTask 3
- BudgetTask 4
The project and the people are fictional. Portraits are generated.
Your route through the job
One bill, from blank lines to the budget the CFO signs. Every task is free.
Measure
Task 1 · 10 min
Carpet as laid, not as bought
- You produce
- Carpet tile area
- Document
- Tender BOQ
- In the ERP
- Bill of Quantities
Measure
Task 2 · 20 min
Gypsum partitions from the drawing
- You produce
- Partition area
- Document
- Tender BOQ
- In the ERP
- PDF Takeoff
Budget
Task 3 · 12 min
Per square foot of what?
- You produce
- Cost per sq ft of carpet
- Document
- Board note
- In the ERP
- Bill of Quantities
Budget
Task 4 · 15 min
The GST that does not come back
- You produce
- Budget with GST
- Document
- Capex approval
- In the ERP
- Bill of Quantities
How one bill becomes a signed budget
Each step below is one task, in the order the tenant needs it.
Blue is what the task adds; grey is carried over from before.
In short. Measure what is built, name the area behind every rate, and budget the GST that does not come back.