All 4 tasks freeIntermediate1 h of studyIndia

Office fit-out: measure, price and budget with GST (India)

A free course of four tasks, about an hour, on an invented office fit-out for a software company.

Workspace: Office fit-out: measure, price and budget with GST (India)
Carpet as laid, not as bought

Who this course is for

Fit-out estimator at the tenant's project management consultant (office interiors) — The project and people are invented for training. The rules and contract forms are real.
Your role in the caseFit-out estimator at the tenant's project management consultant (office interiors)

The project and people are invented for training. The rules and contract forms are real.

You will be able to

Skills checked

  • Measure a floor finish net as laid, deducting only voids over 0.20 m2
  • Take partition areas off a drawing in PDF Takeoff: one face, doors deducted
  • Test a fit-out bill against the cost per sq ft of carpet area, not super built-up
  • Budget a works contract with contingency and the GST that gives no input credit

Tasks

A task as it opens in the trainer, before you enter anything.

Task 1 as it opens in the trainer: Carpet as laid, not as bought
  1. 1
    Carpet as laid, not as boughtFoundation≈10 minTheory · 6 min
  2. 2
    Gypsum partitions from the drawingFoundation≈20 minPDF takeoffTheory · 7 min
  3. 3
    Per square foot of what?Foundation≈12 minTheory · 6 min
  4. 4
    The GST that does not come backFoundation≈15 minTheory · 7 minCheat sheet: every rule on one page

Difficulty is calculated from the steps and the figures you check in each task. Time is the median of real learners once enough have finished; until then it is the author's estimate.

Videos on this method

Certificate

Awarded when all 4 tasks pass the numbers, trace and explain checks.

Certificates

Sample: Certificate of completion
Sample issued to a fictitious learner. Your certificate shows your name, the course, the date and its own ID.
Check this sample

Files you work with

Created in your OpenConstructionERP workspace the moment you enrol.

  • Estimatebill of quantities15 lines
  • Documentsdrawings and model1 file
  • parties3 records

Start free course All courses

What next

Next in the learning pathBid leveling: drywall subcontractor bids (US)Intermediate · 1 h of study

When you pass, add the certificate to LinkedIn from your account. Anyone can open its verification link, no sign-in needed. How to add it

Questions about this course? Write to info@datadrivenconstruction.io