Theory before task 4 · 7 min

GST on a fit-out: a cost the tenant keeps

The GST that does not come back

After this lecture you can

  1. Say why a fit-out is a works contract under GST.
  2. Apply s. 17(5)(c) to a tenant's fit-out.
  3. Put contingency and GST on a bill in the right order.
1 / 3

A fit-out is a works contract

When a contractor builds partitions, ceilings and services into a floor, goods and labour pass together into immovable property. GST treats that as one supply of services, a works contract, taxed at 18 %: 9 % central and 9 % state tax when the supply stays within one state.

Example. A ₹1 crore fit-out invoice carries ₹18 lakh of GST.
2 / 3

No credit for the tenant

A registered business normally takes credit for the GST it pays. Not here: s. 17(5)(c) blocks credit on works contracts for immovable property unless the buyer is itself a works contractor, and the Explanation brings alterations in, to the extent they are capitalised. A tenant that capitalises its fit-out pays the GST and keeps it.

Example. Budget ₹1 crore of works: ₹1.18 crore leaves the bank and stays spent.
+INR1001+INR52+INR18.903INR1244
  • 1 Works
  • 2 Contingency 5 %
  • 3 GST 18 % on both
  • 4 Budget
Common mistake

GST on the works only

Contingency is money for works not yet drawn. When it is spent, it is invoiced with GST like the rest. GST on the sum of positions alone leaves the tax on the contingency unbudgeted.

Example. Contingency first, then GST on the running total.

Budget for another fit-out

Different numbers from your task.

Not to scale
The problem
  • Sum of positions INR40,000,000.
  • Contingency 5 %; GST 18 %, no credit.
Step 1 of 2

Contingency

Contingency, ₹?

INR40,000,000 × 5 % = INR2,000,000.

Step 2 of 2

Budget

Budget with GST, ₹?

(INR40,000,000 + INR2,000,000) × 1.18 = INR49,560,000.

In short. Works, plus contingency, plus 18 % GST on both; no credit back.

Check yourself

Question 1 of 3

Which buyer can take credit for GST on a works contract for a building?

  • Right. Its own output is a works contract.

  • Blocked by s. 17(5)(c).

  • Capitalising is what brings it in.

Question 2 of 3

Contingency 5 %, GST 18 %. Which line is calculated on the other?

  • Right.

  • Tax is the last line.

  • Then the GST on the contingency is missing.

Question 3 of 3

Sum of positions ₹2,00,00,000; contingency 5 %; GST 18 % on the running total. Budget, ₹?

2,00,00,000 × 1.05 × 1.18 = 2,47,80,000.