Cheat sheet
Office fit-out: measure, price and budget with GST (India)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- Measure what is laid. Zone area, less each void over 0.20 m2; cutting waste stays in the rate.
- How it is built
- Carpet tile area = Zone A − Columns − Riser
- Usual mistake
- The 5 % cutting waste went into the quantity. The bill measures carpet as laid; each bidder prices the waste in the rate.
- At work
- The PMC's estimator measures the floor finishes from the plan before the tender BOQ goes out.
- Rule
- One face, built height, doors out. GP centreline length × 3.00 m, less the D2 openings; the glass front is item 1.2.
- How it is built
- GP partition area = Centreline length, group GP × 3.00 − D2 doors
- Usual mistake
- The height stops at the false ceiling. GP runs 150 mm above it, to 3.00 m, as note 2 on A-101 says.
- At work
- On a fit-out the partitions are taken off the plan in the takeoff tool and checked against the dimensions.
- Rule
- Name the area. Direct Cost ÷ carpet area in sq ft (m2 × 10.7639); super built-up flatters the figure.
- How it is built
- Cost per sq ft = Direct Cost ÷ Carpet area in sq ft
- Usual mistake
- That divides by the super built-up area. It flatters the figure by about 40 %; the board's benchmark is on carpet area.
- At work
- The PMC reports cost per sq ft of carpet area to the client's board at every stage.
- Rule
- GST on a fit-out is a cost. Contingency on the Sum of positions, then 18 % GST on the running total; no credit back.
- How it is built
- Budget = Grand Total
- Usual mistake
- GST is left out, as if the credit came back. For a works contract on immovable property it does not (s. 17(5)(c)): budget it.
- At work
- The PMC's cost plan states contingency and GST as separate lines, so the board sees both.