A quantity is what is built
A bill of quantities lists the work as it will stand finished. Every bidder prices the same quantity, so it must be one nobody can argue about: the area of carpet lying on the floor. What a contractor has to buy to get there, offcuts, spares, damaged tiles, is the contractor's own business and goes in the rate.
- Laid: in the quantity INR100
- Waste: in the rate INR5