Theory before task 2 · 7 min

Partitions off a drawing: PDF takeoff

Gypsum partitions from the drawing

After this lecture you can

  1. Calibrate a PDF drawing before measuring.
  2. Measure partitions on the centreline, one type per group.
  3. Turn a length into the billed area: height, faces, openings.
1 / 3

Scale first, then lines

A PDF is a picture until you tell the ERP how long one of its lines is. Pick the longest dimension on the sheet: a small error on a short line grows across the whole floor. Then trace each wall of one type into its own group, along the centreline, so the total of the group is the length the bill wants.

Example. Calibrating on a 4 m wall with a 2 cm click error puts 0.5 % on every length; on a 40 m line, 0.05 %.
2 / 3

From length to area

A partition item describes its build-up: studs, boards on both sides, insulation if any. The bill measures its area once, on one face, at the height that is built, which for most office partitions runs above the false ceiling to close the void for sound. Door openings come out; the doors are their own item.

Example. 25 m of partition, 3.20 m high, three doors of 0.90 × 2.10: 80.00 − 5.67 = 74.33 m2.
+INR801−INR5.672INR74.333
  • 1 Length × height
  • 2 Doors
  • 3 Billed area
Common mistake

Measuring what you see

From the office floor a partition ends at the ceiling tiles. The contractor builds it 150 mm or more above them. Measuring to the visible ceiling leaves that strip unpriced on every wall of the floor.

Example. Read the drawing note for the built height.

Area of another partition run

Different numbers from your task.

Not to scale
The problem
  • Centreline length 25.0 m m; built height 3.2 m m.
  • Three doors, 0.90 × 2.10 m each.
Step 1 of 2

Gross

Length × height, m2?

25.0 m × 3.2 m = 80.00 m².

Step 2 of 2

Net

Billed area, m2?

80.00 m² − 3 × 1.89 = 74.33 m².

In short. Centreline length × built height, one face, openings out.

Check yourself

Question 1 of 3

Which dimension do you calibrate on?

  • Right. Click errors shrink in proportion.

  • The opposite.

  • It uses what you give it.

Question 2 of 3

A glazed front and a gypsum wall meet at a corner. Same group?

  • Right.

  • They are priced differently.

  • The bill separates by type.

Question 3 of 3

30 m of partition, built height 2.90 m, no doors. Billed area, m2?

30 × 2.90 = 87.00.