Course introduction · 3 min

Handover: O&M data, defects and retention release

Mixed-use building, 6 storeys · Handover to the client · Fictional project

You are the main contractor's site manager on a six-storey mixed-use building under a FIDIC Red Book contract. The frame is long finished; now the building must pass to the client with its information, its snags sorted, a year of defects behind it and the Retention Money released. Five tasks take you from the O&M manuals to the last payment.

Start task 1

Job
Mixed-use building, 6 storeys, from taking-over to the end of the defects period
Contract
FIDIC Red Book 2017, US dollars
Standards
ISO 19650-3 and ISO 55000 for the asset information
Work in the ERP
5 tasks, about 1 h 22 min

Who hands what to whom

Every arrow is something that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • MEP subcontractorO&M manuals and asset data
    • ManualsTask 1
    • Asset dataTask 2
  • The EngineerInspects and certifies
    • SnagsTask 3
    • CertificatesTask 5
YouSite manager

Goes from you

    • Defect noticesTask 4
    Client's facility managerRuns the building

Your route through the job

One handover, in the order it happens on site. Every task is free.

  1. Before taking-over

    Task 1 · 12 min

    O&M manuals before taking-over

    You produce
    Package completeness
    Document
    O&M and as-built package
    In the ERP
    Handover & Closeout
  2. Before taking-over

    Task 2 · 15 min

    Asset data against the client's requirements

    You produce
    Asset data compliance
    Document
    Component sheet
    In the ERP
    Inspections
  3. Before taking-over

    Task 3 · 15 min

    Punch list before the Taking-Over Certificate

    You produce
    What stops the TOC
    Document
    Punch list
    In the ERP
    Punch List
  4. Defects period

    Task 4 · 25 min

    The Defects Notification Period register

    You produce
    Defects remedied late
    Document
    DNP register
    In the ERP
    Warranties & Defects Liability
  5. Money

    Task 5 · 15 min

    The two halves of the Retention Money

    You produce
    Both halves of the retention
    Document
    Payment certificates
    In the ERP
    Warranties & Defects Liability

How a building passes to its owner

Each step below is one task, in the order the handover runs.

OutstandingAccepted
Task 1InformationAccepted documents only.
FailPass
Task 2Asset dataEvery rule on every row.
ListedFix first
Task 3Taking-overSafety and use decide.
LateIn time
Task 4DefectsEach on its own date.
Second halfFirst half
Task 5RetentionTwo halves, one deduction.

Blue is what the task adds; grey is carried over from before.

In short. Hand over accepted information, fix what is unsafe, measure every defect against its own date, and release the retention in two halves.