Course introduction · 3 min
Handover: O&M data, defects and retention release
Mixed-use building, 6 storeys · Handover to the client · Fictional project
You are the main contractor's site manager on a six-storey mixed-use building under a FIDIC Red Book contract. The frame is long finished; now the building must pass to the client with its information, its snags sorted, a year of defects behind it and the Retention Money released. Five tasks take you from the O&M manuals to the last payment.
- Job
- Mixed-use building, 6 storeys, from taking-over to the end of the defects period
- Contract
- FIDIC Red Book 2017, US dollars
- Standards
- ISO 19650-3 and ISO 55000 for the asset information
- Work in the ERP
- 5 tasks, about 1 h 22 min
Who hands what to whom
Every arrow is something that reaches your desk or leaves it, and the task where that happens.
Comes to you
- MEP subcontractorO&M manuals and asset data
- ManualsTask 1
- Asset dataTask 2
- The EngineerInspects and certifies
- SnagsTask 3
- CertificatesTask 5
Goes from you
- Defect noticesTask 4
Your route through the job
One handover, in the order it happens on site. Every task is free.
Before taking-over
Task 1 · 12 min
O&M manuals before taking-over
- You produce
- Package completeness
- Document
- O&M and as-built package
- In the ERP
- Handover & Closeout
Before taking-over
Task 2 · 15 min
Asset data against the client's requirements
- You produce
- Asset data compliance
- Document
- Component sheet
- In the ERP
- Inspections
Before taking-over
Task 3 · 15 min
Punch list before the Taking-Over Certificate
- You produce
- What stops the TOC
- Document
- Punch list
- In the ERP
- Punch List
Defects period
Task 4 · 25 min
The Defects Notification Period register
- You produce
- Defects remedied late
- Document
- DNP register
- In the ERP
- Warranties & Defects Liability
Money
Task 5 · 15 min
The two halves of the Retention Money
- You produce
- Both halves of the retention
- Document
- Payment certificates
- In the ERP
- Warranties & Defects Liability
How a building passes to its owner
Each step below is one task, in the order the handover runs.
Blue is what the task adds; grey is carried over from before.
In short. Hand over accepted information, fix what is unsafe, measure every defect against its own date, and release the retention in two halves.