What the client needs on day one
From the date of completion the Employer runs the building. That needs as-built records, operation and maintenance manuals, test certificates, training and asset data. Under FIDIC, where the Contract asks for as-built records and O&M manuals, they are among the conditions for taking-over (10.1 with 4.4).