Theory before task 1 · 7 min

Handover information: delivered is not accepted

O&M manuals before taking-over

Course introduction

After this lecture you can

  1. Name the documents a client needs before taking-over.
  2. Tell a delivered document from an accepted one.
  3. Work out how complete a handover package is.
1 / 3

What the client needs on day one

From the date of completion the Employer runs the building. That needs as-built records, operation and maintenance manuals, test certificates, training and asset data. Under FIDIC, where the Contract asks for as-built records and O&M manuals, they are among the conditions for taking-over (10.1 with 4.4).

Example. A warehouse handed over without its sprinkler manual cannot be insured, however finished it looks.
2 / 3

Accepted information only

ISO 19650 separates delivery from acceptance. Each document is reviewed; accepted ones pass into the asset information model of ISO 19650-3, which the owner uses to run the asset (ISO 55000). Returned ones go back to their author.

Example. Twelve manuals delivered and eight accepted is a package two thirds complete, not a full one.
83
  • Accepted 8
  • Returned 3
  • Not delivered 1
Common mistake

Counting arrivals

A manual that arrived is ticked off, and the package looks ready weeks before it is. The returned manual comes back after the TOC, if ever, and the client's facility team inherits the gap.

Example. Report the package by accepted items, out of every required item, every week before the application.

Completeness of a handover package

Different numbers from your task.

Not to scale
The problem
  • The package has 12 required items.
  • The review accepted 8; three were returned and one is not yet delivered.
Step 1 of 1

Completeness

How complete is the package, in %?

8 × 100 ÷ 12 = 66.67 %.

In short. Completeness counts accepted items only.

Check yourself

Question 1 of 3

A manual was delivered but returned for missing content. Does it count?

  • Right. Delivery is not acceptance.

  • Timing is not the test.

  • An item is accepted or it is not.

Question 2 of 3

Who uses the asset information after handover?

  • Right. That is the point of ISO 55000 asset management.

  • The Engineer certifies; the owner runs the asset.

  • It is the owner's information for this asset.

Question 3 of 3

A package has 20 required items; 13 are accepted. How complete is it, in %?

13 × 100 ÷ 20 = 65 %.