Theory before task 3 · 7 min

What may stay open at taking-over

Punch list before the Taking-Over Certificate

After this lecture you can

  1. Say what FIDIC 10.1 allows to stay open at taking-over.
  2. Sort open snags by their effect on safety and use.
  3. Follow a snag from open to closed.
1 / 3

Application and inspection

The Contractor applies for the Taking-Over Certificate not earlier than 14 days before it expects the Works to be complete. Within 28 days the Engineer issues the certificate, stating the date of completion, or tells the Contractor what is still to be done.

Example. Works expected to be complete on a Friday allow an application two weeks before, on the Friday before last.
2 / 3

Minor items may be listed

The certificate may list minor outstanding work and defects that do not substantially affect safety or use. They are finished in the Defects Notification Period. An item that is a safety risk, or stops the Works being used, must be put right first.

Example. A missing stair handrail stops taking-over; a scratched kitchen door does not.
Fix before the TOC
2
List in the TOC
6
Common mistake

Sorting by priority

High priority on the punch list is a site label, not the contract test. A high item already fixed does not count; a medium item that blocks a fire exit does.

Example. Ask of each open item: is it safe, and can the Employer use the Works?

Sorting open snags

Different numbers from your task.

Not to scale
The problem
  • 9 snags are open after the inspection.
  • 2 are safety risks and 1 stops a floor being used.
Step 1 of 2

Blockers

How many stop the certificate?

2 + 1 = 3.

Step 2 of 2

Listed

How many can be listed in the certificate?

9 − 3 = 6.

In short. Safety and use decide; minor items are listed and finished in the DNP.

Check yourself

Question 1 of 3

Who verifies a snag the Contractor has resolved?

  • Right. The punch list keeps the two steps apart.

  • Then nobody checks the work.

  • Resolved waits for verification.

Question 2 of 3

A low-priority snag blocks the only accessible entrance. Does it stop taking-over?

  • Right. The effect decides, not the label.

  • Priority is a site label.

  • The Engineer applies the test at inspection.

Question 3 of 3

12 snags open; 3 are safety risks, none stop use. How many can be listed in the TOC?

12 − 3 = 9.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.