One period, many clocks
The DNP runs from the date of completion stated in the TOC, for the length in the Contract Data. During it the Employer notifies defects and the Contractor remedies them. Each notice, and the TOC list, sets its own date.
Theory before task 4 · 9 min
The Defects Notification Period register
The DNP runs from the date of completion stated in the TOC, for the length in the Contract Data. During it the Employer notifies defects and the Contractor remedies them. Each notice, and the TOC list, sets its own date.
If a defect is not remedied, the Employer may fix a final date by notice. If that passes, the Employer may have the work done by others at the Contractor's cost (11.4), recovered as a claim and agreed or determined by the Engineer.
Measuring every defect against the DNP expiry hides a repair that took twice its time, and wrongly flags one notified late in the period. A defect notified before expiry is remedied after it if its own date allows.
Different numbers from your task.
On which day of the period was it due?
Hint: The notice day plus the days the notice gives.
How many days late was the repair?
Hint: Remedied day less due day.
Right.
Any defect notified in the period counts.
No extension is needed to remedy it.
Right. Late is recorded, not charged.
FIDIC has no such penalty.
Extension (11.3) is for Works that cannot be used.
Free official texts. The lecture cites clause numbers and puts the rules in its own words.
The Defects Notification Period, defect notices, and what happens when a defect is not remedied (11.4).
The certificate that marks acceptance of the Works, and when it is due.