Theory before task 4 · 9 min

The Defects Notification Period, defect by defect

The Defects Notification Period register

After this lecture you can

  1. Work out when the DNP expires.
  2. Give each defect its own remedy date.
  3. Say what happens when a defect is not remedied (11.4).
1 / 3

One period, many clocks

The DNP runs from the date of completion stated in the TOC, for the length in the Contract Data. During it the Employer notifies defects and the Contractor remedies them. Each notice, and the TOC list, sets its own date.

Example. A 365-day period that crosses 29 February ends a day before the anniversary.
2 / 3

When the Contractor does not remedy

If a defect is not remedied, the Employer may fix a final date by notice. If that passes, the Employer may have the work done by others at the Contractor's cost (11.4), recovered as a claim and agreed or determined by the Engineer.

Example. A loose tile left for weeks is relaid by the Employer's own contractor, and the cost comes back to the Contractor.
+281+142423
  • 1 Notice
  • 2 Final date fixed
  • 3 Days to remedy by others
Common mistake

One deadline for all

Measuring every defect against the DNP expiry hides a repair that took twice its time, and wrongly flags one notified late in the period. A defect notified before expiry is remedied after it if its own date allows.

Example. Put the due date on every defect when you register it.

Remedy dates

Different numbers from your task.

Not to scale
The problem
  • Each notice gives 30 days to remedy.
  • A defect notified on day 100 of the period was remedied on day 136; the final date fixed was 14 days after its due date.
Step 1 of 2

Due day

On which day of the period was it due?

100 + 30 = 130.

Step 2 of 2

Late by

How many days late was the repair?

136 − 130 = 6.

In short. Each defect against its own date; remedied late is still remedied by the Contractor.

Check yourself

Question 1 of 3

A defect is notified a week before the DNP expires. Must the Contractor remedy it?

  • Right.

  • Any defect notified in the period counts.

  • No extension is needed to remedy it.

Question 2 of 3

The Contractor remedies a defect a week late. What follows under 11.4?

  • Right. Late is recorded, not charged.

  • FIDIC has no such penalty.

  • Extension (11.3) is for Works that cannot be used.

Question 3 of 3

A DNP of 365 days starts on 1 March 2027. How many days after 1 March 2028 does it expire?

1 March 2027 + 365 days = 29 February 2028, which is 1 day before 1 March: −1.