Held up to a limit
Retention is deducted from each interim valuation at the rate in the Contract Data, until it reaches the limit of Retention Money, a share of the Accepted Contract Amount. After that nothing more is held.
Theory before task 5 · 8 min
The two halves of the Retention Money
Retention is deducted from each interim valuation at the rate in the Contract Data, until it reaches the limit of Retention Money, a share of the Accepted Contract Amount. After that nothing more is held.
FIDIC 14.9: the first half is certified after the Taking-Over Certificate, the balance after the latest Defects Notification Period expires. The Performance Certificate follows within 28 days of that expiry, once every defect is remedied (11.9).
Only the Employer's own cost of a defect remedied by others is recovered, at the figure the Engineer agreed or determined. A defect the Contractor remedied, even late, cost the Employer nothing.
Different numbers from your task.
Released after the TOC?
Hint: Half of the limit.
Net amount after the DNP?
Hint: The other half less the Engineer's figure.
Right. Deductions stop at the limit.
Only up to the limit.
The rate applies to valuations, and only up to the limit.
Right. FIDIC 14.9.
That is the first half.
It does not wait for the final account.
Free official texts. The lecture cites clause numbers and puts the rules in its own words.
The two-stage release: after the TOC and after the DNP.
The certificate that marks acceptance of the Works, and when it is due.
The Defects Notification Period, defect notices, and what happens when a defect is not remedied (11.4).