Theory before task 5 · 8 min

Retention Money: two halves and one deduction

The two halves of the Retention Money

After this lecture you can

  1. Work out the Retention Money held at the limit.
  2. Release the first half after the TOC and the second after the DNP.
  3. Deduct the Employer's cost of a defect remedied by others.
1 / 3

Held up to a limit

Retention is deducted from each interim valuation at the rate in the Contract Data, until it reaches the limit of Retention Money, a share of the Accepted Contract Amount. After that nothing more is held.

Example. On a 2,000,000 contract with a 5 % limit, retention stops at 100,000, however much more is valued.
Accepted Contract Amount$2,000,000
Limit, 5 %$100,000
First half, after the TOC$50,000
2 / 3

Two releases

FIDIC 14.9: the first half is certified after the Taking-Over Certificate, the balance after the latest Defects Notification Period expires. The Performance Certificate follows within 28 days of that expiry, once every defect is remedied (11.9).

Example. Many contracts and countries use other rates and limits, or a bond instead of cash; the two-stage release is the common case.
Common mistake

Charging every late defect

Only the Employer's own cost of a defect remedied by others is recovered, at the figure the Engineer agreed or determined. A defect the Contractor remedied, even late, cost the Employer nothing.

Example. Half of 100,000 is 50,000; less a determined 1,200 for a defect remedied by others, the last certificate pays 48,800.

Releasing the retention

Different numbers from your task.

Not to scale
The problem
  • Accepted Contract Amount $3,000,000; limit 5% of it, reached long before taking-over.
  • Engineer's figure for a defect remedied by others: $1,800.
Step 1 of 2

First half

Released after the TOC?

$3,000,000 × 5% ÷ 2 = $75,000.

Step 2 of 2

Last certificate

Net amount after the DNP?

$75,000 − $1,800 = $73,200.

In short. Held = the limit; half after the TOC, half after the DNP, less what the Employer paid others.

Check yourself

Question 1 of 3

Retention is a share of each valuation, up to a limit of 5 % of the contract. What is held at taking-over on a long job?

  • Right. Deductions stop at the limit.

  • Only up to the limit.

  • The rate applies to valuations, and only up to the limit.

Question 2 of 3

When is the second half released?

  • Right. FIDIC 14.9.

  • That is the first half.

  • It does not wait for the final account.

Question 3 of 3

Limit 150,000 held. Engineer's figure for a defect remedied by others 2,500. Net amount of the certificate after the DNP?

150,000 ÷ 2 − 2,500 = 72,500.