Theory before task 1 · 6 min

The area check: coordinates against the register

A corner in the wrong place: the area check

Course introduction

After this lecture you can

  1. Compute a parcel's area from its corner coordinates.
  2. Compare it with the legal area and judge the difference.
  3. Find a mistyped coordinate on the plan.
1 / 3

A parcel is a ring of corners

A parcel boundary is stored as corners in order, each with an E and an N. The area follows from the corners alone, by the shoelace formula: walk round the ring, multiply each E by the next N and each N by the next E, take half the difference of the two sums. The ERP does this every time a corner is saved.

Example. A rectangle with corners (0, 0), (50, 0), (50, 40), (0, 40) has an area of 2,000 m².
Side along the street, m50.0 m
Side to the back, m40.0 m
Area, m²2,000.00 m²
2 / 3

Two areas, one check

The register keeps a legal area, written when the parcel was first recorded. The computed area comes from today's corners. A small difference is rounding or an old survey; a large one means a corner is wrong. Many registers flag anything beyond about 1 %.

Example. Legal 2,000 m², computed 2,190 m²: 9.5 % off, so look for a corner.
Legal area
USD2,000
Computed area
USD2,190
Common mistake

Fixing the area instead of the corner

When the areas disagree it is tempting to edit the legal area to match. That hides the error: the parcel still has a corner in the wrong place, and the next sale or fence uses it. Find the corner that disagrees with the field book and correct that coordinate.

Example. Two swapped digits in an N of 4,950.17 make 4,590.17: 360 m out, a spike on the plan.
C1C2C3 as typedC3 in the field bookC4C5StreetDevelopment plot
One swapped pair of digits pulls a corner tens of metres out of the outline.

Area of another parcel

Different numbers from your task.

Not to scale
The problem
  • A rectangular parcel 60.0 m by 45.0 m; legal area 2,600.00 m².
Step 1 of 2

Computed area

Area from the corners, m²?

60.0 m × 45.0 m = 2,700.00 m².

Step 2 of 2

Difference

Computed less legal, m²?

2,700.00 m² − 2,600.00 m² = 100.00 m²: about 4 %, so check the corners.

In short. Area from the corners; compare with the legal area; a big gap means a wrong corner.

Check yourself

Question 1 of 2

The computed area is 12 % above the legal area. What do you check first?

  • Right.

  • It is the reference, not the suspect.

  • That changes areas by parts per thousand, not 12 %.

Question 2 of 2

Where does the computed area of a parcel come from?

  • Right.

  • That is the other figure.

  • Not in the ERP: the corners decide.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.