Theory before task 4 · 7 min

Subdivision to an area

Split off lot 1, parallel to the street

After this lecture you can

  1. Split a parcel parallel to a side to a set area.
  2. Explain why a parallel cut is not a rectangle guess.
  3. Read the depth of a new lot from its coordinates.
1 / 3

A cut that makes the area

A buyer pays for an area, not a depth. The surveyor moves a line parallel to the chosen side until the part between them holds exactly that area. The ERP does it by repeated halving: try a depth, compute the area, adjust, until the area matches.

Example. Street side 120 m, sides square to it: 3,000 m² needs 25 m.
Lot 1, for the buyerRest of the plotDepthCut line, parallel to the streetStreet: side C1 to C2C1C2C3C5
The sides lean outward, so the lot is a little wider at the back than at the street.
2 / 3

Leaning sides change the depth

If the side boundaries lean outward, each metre back is wider than the street side, so fewer metres are needed than the rectangle guess. If they lean inward, more are needed. The new corners sit where the cut meets the sides.

Example. Street 120 m, widening to 124 m at 25 m back: the lot is about 24.6 m deep, not 25 m.
Rectangle guess, m
USD25
Leaning sides, m
USD24.60
Common mistake

Area ÷ street length

It is quick and often close, and wrong by tens of square metres on a real plot. On a lot sold by area that is land given away, or land the buyer paid for and did not get.

Example. Compute the cut; then read the depth off the new corners.

Lot on another plot

Different numbers from your task.

Not to scale
The problem
  • Lot of 3,000.00 m² along a street side of 120.0 m; sides square to the street.
Step 1 of 1

Depth

Depth of the lot, m?

3,000.00 m² ÷ 120.0 m = 25.0 m.

In short. Only square sides make area ÷ street length the depth; leaning sides need the computed cut.

Check yourself

Question 1 of 2

The side boundaries lean outward. The true depth is:

  • Right.

  • That is for inward lean.

  • Only for square sides.

Question 2 of 2

What happens to the parent parcel after a split?

  • Right.

  • That counts the land twice.

  • It stays, marked superseded.