Theory before task 2 · 7 min

Cut and fill against a design pad

Platform at 412.000: cut and fill

After this lecture you can

  1. Compute cut and fill between ground and a flat pad.
  2. Find the cut/fill line.
  3. Tell dug from compacted volume.
1 / 3

Two surfaces, one boundary

Cut is where the ground lies above the design; fill is where it lies below. The Volumes module compares a base surface (the ground, earlier) with a compare surface (the pad, later) over the pad's outline and adds up the two parts separately.

Example. Ground 0.40 m above the pad over 50 m2 gives 20 m3 of cut.
CutFillCut/fill linePlatform, west to eastNorth
The heat map in the ERP shows the same split in colour.
2 / 3

The line where cut becomes fill

On evenly sloping ground the cut/fill line is where the ground crosses the design level. On each side the earth forms a wedge: its volume is width × length × depth ÷ 2.

Example. A wedge 20 m wide, 10 m long and 0.30 m deep at its edge: 20 × 10 × 0.30 ÷ 2 = 30 m3.
Width, m20
Length to the line, m10
Depth at the edge, m0.3
Wedge, m330
Common mistake

Balanced as dug, short as placed

Dug soil packs down when it is compacted in fill. A factor from the soils report says how much: 0.90 means 1 m3 dug makes 0.90 m3 of compacted fill. Equal cut and fill as dug leave the fill short.

Example. 80 m3 of cut at 0.85 fills 68 m3: 12 m3 short of an 80 m3 fill.

Shortfall on another pad

Different numbers from your task.

Not to scale
The problem
  • Cut 80 m3 and fill 80 m3 as dug; compaction factor 0.85.
Step 1 of 2

Compacted cut

Cut once compacted, m3?

80 × 0.85 = 68 m3.

Step 2 of 2

Short

Compacted fill short, m3?

80 − 68 = 12 m3.

In short. Compare compacted with compacted: fill less cut × factor.

Check yourself

Question 1 of 2

Base surface is the ground, compare surface the pad. Where is cut?

  • Right.

  • That is fill.

  • Batters can be cut or fill.

Question 2 of 2

Cut 60 m3, compaction factor 0.80, fill 60 m3. Compacted fill short, m3?

60 − 60 × 0.80 = 12 m3.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.