Theory before task 3 · 7 min

The level that balances compacted cut and fill

The level that balances

After this lecture you can

  1. Write cut and fill as functions of the pad level.
  2. Solve for the balanced level.
  3. Check the result in the ERP.
1 / 3

Both wedges move with the level

Lower the pad and the cut wedge grows, the fill wedge shrinks. On an even slope each wedge grows with the square of its depth, so the balance is a short calculation, not trial and error.

Example. Ground falls 0.02 m per m. A wedge 0.40 m deep is 20 m long; 0.20 m deep, 10 m long.
Ground, westGround, eastCutFillPlatform, west edge to east edgeBalanced levelLevel of task 2
Lower the pad and the cut grows while the fill shrinks.
2 / 3

Solve with the square root

With compaction factor k, set k × cut = fill. The width and the slope cancel, and what is left is √k × (high ground − L) = L − low ground. So L = (low + √k × high) ÷ (1 + √k).

Example. High 100.40, low 99.60, k = 0.81 (√k = 0.9): L = (99.60 + 0.9 × 100.40) ÷ 1.9 = 99.979.
Low ground99.6
√k × high ground90.36
Divided by 1 + √k1.9
Balanced level99.98
Common mistake

The factor on the wrong side

The factor shrinks the cut, because the cut is what gets compacted. Putting it on the fill moves the level the wrong way: up instead of down.

Example. With the factor on the fill, the example gives a level above the middle instead of below it.

Balanced level on another slope

Different numbers from your task.

Not to scale
The problem
  • Ground 100.4 at the high edge, 99.6 at the low edge; √k = 0.9.
Step 1 of 2

Level

Balanced level, m?

(99.6 + 0.9 × 100.4) ÷ (1 + 0.9) = 99.98.

Step 2 of 2

Against the middle

How far below the middle level, mm?

The pad sits 21.05 mm below the middle.

In short. √k × (high − L) = L − low; the balanced pad sits a little below the middle.

Check yourself

Question 1 of 2

Compaction factor 1.00. Where is the balanced pad on an even slope?

  • Right. Equal wedges.

  • Only with a factor under 1.

  • Only with a factor over 1.

Question 2 of 2

A pad at the balanced level is built. What should the volume show?

  • Right.

  • That is the dug balance.

  • The pad still cuts the high side.