Theory before task 4 · 7 min

Polar setting out from a monument

Corners from the boundary

After this lecture you can

  1. Turn a bearing and distance into E and N.
  2. Save a computed point.
  3. Check a setback from a boundary.
1 / 3

A bearing starts at north

A survey bearing is measured from grid north, clockwise. From a known point, a bearing and a grid distance give the new point: ΔE = d × sin(bearing), ΔN = d × cos(bearing).

Example. From E 1000.000 N 2000.000, 50.000 m at 30°: ΔE = 25.000, ΔN = 43.301.
C1, monumentC2C3C4C5StreetGrid northBuilding, BC1 to BC4Street setbackBearing and distanceNorth
Bearings start at grid north and turn clockwise.
2 / 3

Check against the boundary

A building corner computed from a monument is only half the job. Its distance from the boundary is checked against the required setback with an independent measure, before any peg goes in.

Example. A boundary running due east at N 2000.000 and a building side at N 2018.500: setback 18.50 m.
N of the building side2,018.5
N of the boundary2,000
Setback, m18.5
Common mistake

The angle from east

Calculators and school maths measure angles from east, anticlockwise. Taken as a bearing, the same number lands the point metres away. Bearings start at north.

Example. 30° from north is 60° from east: confusing them moves a point 50 m away by about 25 m.

A corner from another monument

Different numbers from your task.

Not to scale
The problem
  • Monument at E 1,000, N 2,000; bearing 30°, distance 50 m; sin 30° = 0.5, cos 30° = 0.87.
Step 1 of 2

E

E of the corner?

1,000 + 50 × sin 30° = 1,025.

Step 2 of 2

N

N of the corner?

2,000 + 50 × cos 30° = 2,043.3.

In short. Bearing from north, clockwise; sin for E, cos for N; then check the setback.

Check yourself

Question 1 of 2

A bearing of 90° points which way?

  • Right.

  • That is 0°.

  • That is 270°.

Question 2 of 2

What does the Setback check prove?

  • Right.

  • That is setting-out, task 5.

  • That is the parcel's own check.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.