Theory before task 5 · 6 min

Checking stakes: radial error and diagonals

Stake, check and decide

After this lecture you can

  1. Compute the radial error of a stake.
  2. Decide pass, NCR or accepted deviation.
  3. Check a rectangle by its diagonal.
1 / 3

The miss is a straight line

A stake misses its design point in E and in N. The miss is the straight line between the two points: d = √(dE² + dN²). The verdict compares d with the tolerance.

Example. dE 6 mm, dN 8 mm: d = 10 mm.
Tolerance, 10 mm around the design pointDesigndEdNStake, as measuredd, the straight-line miss
Not to scale: the miss is drawn large to be seen.
2 / 3

The diagonal checks the shape

Four stakes can each pass and still make a parallelogram. Measure a diagonal and compare it with √(length² + width²): the difference shows a twist or a wrong size that no single stake shows.

Example. Design 30 × 16 m: diagonal 34.000 m. Measured 33.994 m: error −6 mm.
Design diagonal, m34.000
Measured diagonal, m33.994
Error, mm-6
Common mistake

Accept and move on

A stake outside tolerance is reset, or the deviation is formally accepted by whoever may accept it. Pressing Accept deviation to clear the screen hides a fault that the concrete will keep.

Example. A corner 15 mm out on a 10 mm tolerance gets an NCR draft, not a quiet acceptance.

Another stake and diagonal

Different numbers from your task.

Not to scale
The problem
  • A stake is 6 mm off in E and 8 mm off in N. A 30 × 16 m rectangle measures 33.994 m on its diagonal.
Step 1 of 2

Radial error

d of the stake, mm?

√(6² + 8²) = 10 mm.

Step 2 of 2

Diagonal

Error of the diagonal, measured less design, mm?

(33.994 − 34.000) × 1,000 = -6 mm.

In short. Radial miss against the tolerance; one diagonal against √(L² + W²).

Check yourself

Question 1 of 2

dE 3 mm, dN 4 mm, tolerance 10 mm. Verdict?

  • Right.

  • Components do not add.

  • √(9 + 16) = 5.

Question 2 of 2

A stake fails. What does the record need?

  • Right.

  • Each point is decided.

  • The design stays; the stake moves.