Course introduction · 3 min

Site safety: risk, permits, incidents and LTIFR

Mixed-use building, 6 storeys · Month 6 safety · Fictional project

You are the main contractor's health and safety lead on a six-storey mixed-use building under a FIDIC Red Book contract. It is October, month 6: the frame climbs past level 3 and the services start. In five tasks you keep a month of site work safe and report it: hazards before a pour, the controls that let it go ahead, the week's permits, a near miss investigated with the gang, and the LTIFR for the Engineer.

Start task 1

Job
Mixed-use building, 6 storeys, month 6 of 18
Contract
FIDIC Red Book 2017, Contractor's health and safety duties (4.8, 6.7)
Method
ISO 45001: risk assessment, hierarchy of controls, incident investigation, worker participation
Work in the ERP
5 tasks, about 1 h 35 min

Who hands what to whom

Every arrow is something that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • Site managerRuns the pour and the look-ahead
    • Pre-pour walkTask 1
    • The week's jobsTask 3
  • Concrete frame subcontractorThe gang on the deck
    • The loading gateTask 4
YouHealth and safety lead

Goes from you

    • LTIFR and incidentsTask 5
    The EngineerReads the monthly report

Your route through the job

One month on site, in the order it happens. Every task is free.

  1. Before the work

    Task 1 · 10 min

    Risk before the pour: severity times likelihood

    You produce
    Hazards that stop the pour
    Document
    Pre-pour risk assessment
    In the ERP
    Safety
  2. Before the work

    Task 2 · 20 min

    The hierarchy of controls and residual risk

    You produce
    Residual risk after controls
    Document
    Observations
    In the ERP
    Safety
  3. Before the work

    Task 3 · 20 min

    Permits to work for the week

    You produce
    The week's permits
    Document
    Permit to work
    In the ERP
    HSE Management
  4. When it goes wrong

    Task 4 · 20 min

    A near miss, its investigation and the toolbox talk

    You produce
    Root cause and a new control
    Document
    Incident and toolbox talk
    In the ERP
    Safety, HSE Management
  5. Report

    Task 5 · 25 min

    Lost time and the LTIFR for the client's report

    You produce
    Lost-time injuries and LTIFR
    Document
    Monthly safety report
    In the ERP
    Safety

How a site stays safe and proves it

Each step below is one task, in the order a month runs.

Risk
Task 1AssessScore each hazard; the tier decides.
RemovedResidual
Task 2ControlHighest control first; rescore.
Checks
Task 3PermitNamed jobs get named checks.
Lesson
Task 4InvestigateNear miss: fix the system.
LTIHours
Task 5ReportLost time per million hours.

Blue is what the task adds; grey is carried over from before.

In short. Assess before the work, control from the top of the hierarchy, permit the jobs the rule names, learn from every incident, and report the rate with the events behind it.