Course introduction · 3 min
Site safety: risk, permits, incidents and LTIFR
Mixed-use building, 6 storeys · Month 6 safety · Fictional project
You are the main contractor's health and safety lead on a six-storey mixed-use building under a FIDIC Red Book contract. It is October, month 6: the frame climbs past level 3 and the services start. In five tasks you keep a month of site work safe and report it: hazards before a pour, the controls that let it go ahead, the week's permits, a near miss investigated with the gang, and the LTIFR for the Engineer.
- Job
- Mixed-use building, 6 storeys, month 6 of 18
- Contract
- FIDIC Red Book 2017, Contractor's health and safety duties (4.8, 6.7)
- Method
- ISO 45001: risk assessment, hierarchy of controls, incident investigation, worker participation
- Work in the ERP
- 5 tasks, about 1 h 35 min
Who hands what to whom
Every arrow is something that reaches your desk or leaves it, and the task where that happens.
Comes to you
- Site managerRuns the pour and the look-ahead
- Pre-pour walkTask 1
- The week's jobsTask 3
- Concrete frame subcontractorThe gang on the deck
- The loading gateTask 4
Goes from you
- LTIFR and incidentsTask 5
Your route through the job
One month on site, in the order it happens. Every task is free.
Before the work
Task 1 · 10 min
Risk before the pour: severity times likelihood
- You produce
- Hazards that stop the pour
- Document
- Pre-pour risk assessment
- In the ERP
- Safety
Before the work
Task 2 · 20 min
The hierarchy of controls and residual risk
- You produce
- Residual risk after controls
- Document
- Observations
- In the ERP
- Safety
Before the work
Task 3 · 20 min
Permits to work for the week
- You produce
- The week's permits
- Document
- Permit to work
- In the ERP
- HSE Management
When it goes wrong
Task 4 · 20 min
A near miss, its investigation and the toolbox talk
- You produce
- Root cause and a new control
- Document
- Incident and toolbox talk
- In the ERP
- Safety, HSE Management
Report
Task 5 · 25 min
Lost time and the LTIFR for the client's report
- You produce
- Lost-time injuries and LTIFR
- Document
- Monthly safety report
- In the ERP
- Safety
How a site stays safe and proves it
Each step below is one task, in the order a month runs.
Blue is what the task adds; grey is carried over from before.
In short. Assess before the work, control from the top of the hierarchy, permit the jobs the rule names, learn from every incident, and report the rate with the events behind it.