Theory before task 1 · 7 min

Risk assessment: severity times likelihood

Risk before the pour: severity times likelihood

Course introduction

After this lecture you can

  1. Say what severity and likelihood each measure.
  2. Score a hazard on a 5 × 5 matrix.
  3. Decide from the tier what happens before work starts.
1 / 3

Two questions per hazard

How bad could the harm be? That is severity. How probable is it, with the work done as it is done today? That is likelihood. Each is rated 1 to 5 against words the whole site shares, and the score is their product. ISO 45001 6.1.2 asks for a process like this; the matrix and its words are the company's own.

Example. A trench 1.8 m deep with no support, men working in it every day: severity 4, likelihood 4, score 16.
Unsupported trench
$16
Trip on loose cable
$6
Dust from sweeping
$4
2 / 3

The tier decides

The score falls into a tier, and each tier names an action. Critical stops the work. High lets it start only with controls in place and checked. Medium is planned within the week; low is kept under review. The tier turns a number into a decision someone can act on.

Example. On a different site a high score means: controls first, checked by the site manager, then the work.
Common mistake

Judging by severity alone

A fatal consequence feels like a stop. But a hazard people rarely meet scores lower than one they meet every hour. Stopping on severity alone stops the wrong work and leaves the frequent hazards running.

Example. Severity 5 with likelihood 1 scores 5, low. Severity 4 with likelihood 4 scores 16, critical.

Scores and tiers on another site

Different numbers from your task.

Not to scale
The problem
  • Trench: severity 4, likelihood 4.
  • Crane near a road: severity 5, likelihood 1.
Step 1 of 2

Trench

Score of the trench?

4 × 4 = 16: critical, the work stops.

Step 2 of 2

Crane

Score of the crane?

5 × 1 = 5: low, despite the fatal severity.

In short. Score = severity × likelihood; the tier, not the severity, decides.

Check yourself

Question 1 of 3

A hazard is in the high tier. What does the site do?

  • Right. High means controls first, then the work.

  • Stop is for the critical tier.

  • That is the medium tier.

Question 2 of 3

Who should take part in finding hazards?

  • Right. ISO 45001 5.4.

  • One person sees less than a gang.

  • The client is not on the deck.

Question 3 of 3

Severity 3, likelihood 3. Score?

3 × 3 = 9: medium.