Theory before task 4 · 6 min

Correct the book, charge the cause

Close the gap: adjust the book, charge the supplier

After this lecture you can

  1. Read a variance against book stock.
  2. Propose and confirm a stock adjustment.
  3. Price only what the supplier caused.
1 / 3

The book follows the measurement

Book stock is what the paperwork says arrived. The survey says what is on the ground. When the gap is beyond the tolerance, the book is corrected to the survey by an adjustment that one person proposes and another confirms. Nothing moves in the inventory before that.

Example. Book 520 t, survey 498 t, tolerance 3 %: −22 t is −4.2 %, so the book is adjusted by −22 t.
+USD5201−USD222USD4983
  • 1 Book stock
  • 2 Adjustment
  • 3 Book after
2 / 3

The money follows the cause

The variance mixes several causes: a duplicated ticket, a density that was too high, the small error of the survey. The supplier owes back only what it caused and invoiced: the duplicated load at the contract price.

Example. Duplicated load 24.0 t at USD 20.00: USD 480.00, even if the variance is larger.
Duplicated load, t24
Price per tonne, USDUSD20.00
Deduction, USDUSD480.00
Common mistake

Charging the whole variance

The whole gap at the price feels fair, but part of it is your own density and survey. Charged to the supplier, it is a deduction you cannot defend.

Example. Charge the cause you can show on a ticket.

Deduction on another invoice

Different numbers from your task.

Not to scale
The problem
  • A load of 24 t was invoiced twice at USD USD20.00 per tonne.
Step 1 of 1

Deduction

Deduction, USD?

24 × USD20.00 = USD480.00.

In short. Book stock to the survey by a confirmed adjustment; the invoice loses the duplicated load.

Check yourself

Question 1 of 2

Who moves the inventory after a stockpile survey?

  • Right.

  • Saving only proposes nothing.

  • The supplier does not keep your book.

Question 2 of 2

The variance is larger than the duplicated load. What do you charge?

  • Right.

  • Part of it is yours.

  • The duplicate is already proven.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.