Theory before task 3 · 6 min

Tickets and survey: two measurements of one heap

Tickets against the heap

After this lecture you can

  1. Compare delivered tonnes with a surveyed heap.
  2. Spot a duplicated ticket.
  3. Know what a threshold can hide.
1 / 3

Weighed in, measured on the ground

Each load is weighed at the weighbridge and its ticket booked to the heap. The survey measures the heap itself. If both are right they agree within the error of the density and the survey. A gap far beyond that is a record problem: a ticket missing, a ticket twice, or a load tipped elsewhere.

Example. 20 tickets of about 25 t against a heap that, with the lab density, holds about 480 t.
SS-0418SS-0418S1 sandSame number, same supplier: one load, entered twice
One copy is the delivery, the other is the duplicate.
2 / 3

What a green band hides

A panel that turns amber beyond 10 % stays green for any gap smaller than that. One load on a heap of a dozen loads is about 8 %: a duplicate fits inside the band. Green says the gap is small, not that each ticket is genuine.

Example. 12 loads of 25 t: one duplicate adds 25 t to 300 t, 8.3 %, still green.
One load in twelve
USD8.30
Threshold
USD10
Common mistake

Rejecting both copies

When a number appears twice, it is tempting to reject both to be safe. One load did arrive: the weighbridge and the heap show it. Reject the copy, keep the delivery.

Example. Two rows of ticket 0731: keep the first, reject the second.

Tickets for another heap

Different numbers from your task.

Not to scale
The problem
  • Ten tickets add up to 310 t; one ticket of 25.5 t is entered twice.
Step 1 of 1

Genuine tickets

Tonnes of the genuine tickets?

310 − 25.5 = 284.5 t.

In short. Remove the duplicate once, then compare the genuine tickets with the survey.

Check yourself

Question 1 of 2

A ticket number appears twice for one supplier. What do you reject?

  • Right.

  • One load arrived.

  • Green does not prove each ticket.

Question 2 of 2

Why does a duplicate often stay inside a 10 % band?

  • Right.

  • It only sees the total.

  • They carry the full tonnes.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.