Theory before task 2 · 6 min

Loose bulk density: from cubic metres to tonnes

Density turns cubic metres into tonnes

After this lecture you can

  1. Tell loose, compacted and particle density apart.
  2. Average repeat tests correctly.
  3. Turn a volume into tonnes and compare two densities.
1 / 3

Three densities of one sand

Grains alone are heavy, about 2.6 t/m3. Poured loose into a heap they leave air between them, so a cubic metre weighs much less. Rolled into a fill, the same sand packs closer and weighs more again. A heap is loose: its tonnes come from the loose bulk density.

Example. One sand: particles 2.65, loose 1.45, compacted 1.80 t/m3.
Particles
USD2.65
Loose
USD1.45
Compacted
USD1.80
2 / 3

The test and its mean

The lab fills a container of known volume without compaction, strikes it level and weighs it. Mass over volume is one result. Samples differ a little, so the lab repeats the test and reports the mean.

Example. Samples 1.42, 1.46, 1.44 t/m3: mean 1.44 t/m3.
Sum of three samples, t/m34.32
Mean, t/m31.44
Common mistake

The supplier's density stays in

The supplier's paperwork carries a density, often a round book figure. Left in the survey, it decides the tonnes on the books. A few hundredths of a tonne per cubic metre over a whole heap is a load or more.

Example. A 500 m3 heap at 1.50 instead of 1.44: 30 t more on the books than in the heap.

Tonnes for another heap

Different numbers from your task.

Not to scale
The problem
  • Heap 500 m3; supplier's density 1.5 t/m3; lab mean 1.44 t/m3.
Step 1 of 2

Measured tonnes

Tonnes at the lab mean?

500 × 1.44 = 720 t.

Step 2 of 2

Over-statement

Tonnes the supplier's density over-states?

500 × 1.5 − 720 = 30 t.

In short. Tonnes = volume × loose bulk density, the mean of repeat tests.

Check yourself

Question 1 of 2

Which density belongs to a tipped heap?

  • Right.

  • Nobody rolled the heap.

  • That leaves out the voids.

Question 2 of 2

A 300 m3 heap: supplier 1.50, lab 1.40 t/m3. Tonnes over-stated?

300 × 1.50 − 300 × 1.40 = 30 t.

Read the source