Theory before task 1 · 6 min

A heap is the space between two surfaces

One heap, one volume

Course introduction

After this lecture you can

  1. Say what a stockpile volume measures.
  2. Build a surface from survey points.
  3. Check a heap's volume by hand.
1 / 3

Two models of the same ground

Before tipping, the surveyor shoots the pad the heap will stand on: that is the base. After tipping, the rover walks the heap: toe, crest, points on the slopes and the top. Each set of points becomes a surface of triangles. The volume is what lies between the two surfaces, over the same area.

Example. A pad shot on a 5 m grid; a heap shot along its toe every 2 m, along its crest and across its slopes.
NorthToe: foot of the heapCrest: edge of the flat topSectionCross: ground point before tippingDots: rover points on the toe, slopes, crest and top
The base comes from the crosses, the pile surface from the dots.
2 / 3

A check by hand

A heap with a flat top is close to a prismoid. Its volume is the height over six times the sum of the base area, four times the area halfway up, and the top area. The system's figure from the two surfaces should land within a few per cent of it.

Example. Base 12 × 8 m, top 4 × 2 m, height 2 m: halfway 8 × 5 = 40 m2; 2 ÷ 6 × (96 + 160 + 8) = 88 m3.
Base area, m296.00 m²
Four times the middle area, m2160.00 m²
Top area, m28.00 m²
Volume, m388
Common mistake

The box over the toe

Length × width × height of the toe treats the heap as a block. The slopes leave the corners empty, so the box is often close to twice the real volume. The same mistake turns up when a pile surface is measured down to a flat level that is not the ground.

Example. The 12 × 8 × 2 m heap above as a box: 192 m3, more than twice the 88 m3 it holds.

Volume of another heap

Different numbers from your task.

Not to scale
The problem
  • Base area 96.00 m² m2, area halfway up 40.00 m² m2, top area 8.00 m² m2, height 2.0 m m.
Step 1 of 2

Weighted areas

Base + 4 × middle + top, m2?

96.00 m² + 4 × 40.00 m² + 8.00 m² = 264.00 m².

Step 2 of 2

Volume

Volume, m3?

2.0 m ÷ 6 × 264.00 m² = 88 m3.

In short. Pile surface minus base surface, over the same area; the prismoid is the check by hand.

Check yourself

Question 1 of 2

A heap is shot after tipping, but the pad was never surveyed. What is missing?

  • Right. Without it there is nothing to subtract.

  • The toe gives the edge; the ground under the middle is unknown.

  • Density turns volume into tonnes; it does not give the volume.

Question 2 of 2

Base 10 × 6 m, top 2 × 1 m, height 1.5 m. Which is nearest the real volume?

  • Right: about half the 90 m3 box.

  • That is the box over the toe.

  • Too small: the base alone covers 60 m2.

Read the source