Course introduction · 3 min

Investor's cost estimate: unit prices to award (Poland)

You are the cost estimator a Polish gmina hires for its village hall retrofit. The council votes the budget on Thursday, and the tender follows. In five tasks you price an item from norms, correct the roof quantity, set the contract value and the budget, test the offers for an abnormally low price, and close the gap when the lowest offer is over budget.

Start task 1

Workers fix insulation boards to the old plastered walls of a public building, behind scaffolding with green netting.Fictional project
Kalinowa Struga village hallRetrofit before the winter
Works
Roof covering, ceiling and wall insulation, windows
Procedure
Public Procurement Law, basic procedure, lump-sum price
Method
Investor's estimate (kosztorys inwestorski), then the tender
Work in the ERP
5 tasks, about 1 h 20 min

Who hands what to whom

Every arrow is a figure that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • DesignerDrawings and przedmiar
    • QuantitiesTask 2
  • BiddersFour offers
    • OffersTask 4
YouInvestor's cost estimator

Goes from you

    • BudgetTask 3
    • IncreaseTask 5
    CouncilVotes the budget
    • 30 % linesTask 4
    Tender committeeRuns the procedure

The project and the people are fictional. Portraits are generated.

Your route through the job

One estimate and one tender, in the order the gmina needs them. Every task is free.

  1. Estimate

    Task 1 · 10 min

    A unit price nobody has published

    You produce
    Unit price from norms
    Document
    Kosztorys inwestorski
    In the ERP
    Bill of Quantities
  2. Estimate

    Task 2 · 15 min

    The roof is bigger than its plan

    You produce
    Roof covering area
    Document
    Kosztorys inwestorski
    In the ERP
    Bill of Quantities
  3. Estimate

    Task 3 · 15 min

    Contract value and the budget

    You produce
    Contract value and budget
    Document
    Council resolution
    In the ERP
    Bill of Quantities
  4. Tender

    Task 4 · 20 min

    Too cheap to believe?

    You produce
    Abnormally low price lines
    Document
    Tender file
    In the ERP
    Bid Management
  5. Tender

    Task 5 · 20 min

    The lowest offer is over budget

    You produce
    Budget increase and award
    Document
    Tender file
    In the ERP
    Bid Management

How one estimate carries a public tender

Each step below is one task, in the order the gmina needs it.

Kp ZR M S
Task 1PriceNorms, then Kp and Z.
Roof
Task 2QuantityOn the slope, not the plan.
VATNet
Task 3ValueNet value, gross budget.
Line
Task 4Test30 % below either base.
GapBudget
Task 5AwardRaise the budget or cancel.

Blue is what the task adds; grey is carried over from before.

In short. Price what a contractor would charge, measure what is built, keep value net and budget gross, and test every offer against both.