All 5 tasks freeIntermediate1.5 h of studyPoland

Investor's cost estimate: unit prices to award (Poland)

On an invented village hall retrofit in a Polish gmina.

Workspace: Investor's cost estimate: unit prices to award (Poland)
A unit price nobody has published

Who this course is for

Investor's cost estimator for a gmina — The project and people are invented for training. The rules and contract forms are real.
Your role in the caseInvestor's cost estimator for a gmina

The project and people are invented for training. The rules and contract forms are real.

You will be able to

Skills checked

  • Build a unit price from norms with Kp and Z on their own bases
  • Measure a pitched roof covering on the slope, not on the plan
  • Set the contract value net and the council's budget with VAT
  • Find the abnormally low price lines of art. 224 Pzp
  • Close a tender over budget under art. 255 Pzp: raise the budget or cancel

Tasks

A task as it opens in the trainer, before you enter anything.

Task 1 as it opens in the trainer: A unit price nobody has published
  1. 1
    A unit price nobody has publishedFoundation≈10 minTheory · 7 min
  2. 2
    The roof is bigger than its planFoundation≈15 minTheory · 6 min
  3. 3
    Contract value and the budgetFoundation≈15 minTheory · 6 min
  4. 4
    Too cheap to believe?Foundation≈20 minTenderTheory · 8 min
  5. 5
    The lowest offer is over budgetFoundation≈20 minTenderTheory · 7 minCheat sheet: every rule on one page

Difficulty is calculated from the steps and the figures you check in each task. Time is the median of real learners once enough have finished; until then it is the author's estimate.

Videos on this method

Certificate

Awarded when all 5 tasks pass the numbers, trace and explain checks.

Certificates

Sample: Certificate of completion
Sample issued to a fictitious learner. Your certificate shows your name, the course, the date and its own ID.
Check this sample

Files you work with

Created in your OpenConstructionERP workspace the moment you enrol.

  • Estimatebill of quantities6 lines
  • Tenderbid package1 line
  • parties6 records

Start free course All courses

What next

When you pass, add the certificate to LinkedIn from your account. Anyone can open its verification link, no sign-in needed. How to add it

Questions about this course? Write to info@datadrivenconstruction.io

Related courses

Start free: task 1 of 5All 5 tasks free · 1.5 h of study

Start free course