The quantities under the budget
The przedmiar is part of the design documents: the list of works with their quantities. The investor's estimate multiplies those quantities by unit prices, so a short quantity becomes a short contract value and a short budget. The specification for each item says how it is measured; for a roof covering, the area of the slopes with the overhangs.