Theory before task 3 · 6 min

Contract value and budget: net and gross

Contract value and the budget

After this lecture you can

  1. Define the contract value of works under Pzp.
  2. Add VAT once, on the estimate total.
  3. Keep the regional markup set off a kosztorys of full unit prices.
1 / 3

Two numbers, two jobs

The contract value (wartość zamówienia) is the contractor's whole estimated price without VAT. It decides whether the Act applies (130,000 zł) and which procedure fits. The budget is what the gmina will spend, VAT included, and the council votes it. Both come out of the same estimate, one before VAT, one after.

Example. An estimate of 400,000 zł net is a contract value of 400,000 zł and a budget of 492,000 zł.
PLN400,000PLN92,000
  • Estimate, net PLN400,000
  • VAT 23 % PLN92,000
2 / 3

Six months of life

A contract value of works may be set no earlier than six months before the procedure starts. If the tender slips past that, the estimate is updated to current prices before the notice goes out.

Example. Estimate in November, notice in January: in time. Notice in June: update first.
Common mistake

Overheads twice

The ERP offers a regional markup set with Kp, Z, a reserve and VAT for bills priced at direct cost. An investor's estimate of full unit prices already holds Kp and Z. Applying the set adds them again and inflates the budget by a third.

Example. Only VAT goes on top of full unit prices.

Value and budget of another estimate

Different numbers from your task.

Not to scale
The problem
  • Sum of positions PLN400,000, unit prices with Kp and Z.
  • VAT 23 %.
Step 1 of 2

Contract value

Contract value, net?

The Sum of positions: PLN400,000.

Step 2 of 2

Budget

Budget with VAT?

PLN400,000 × 1.23 = PLN492,000.

In short. Value net, budget gross, VAT once.

Check yourself

Question 1 of 3

The contract value decides whether the Act applies. Net or gross?

  • Right. Art. 28.

  • Thresholds compare net values.

  • The Act fixes it.

Question 2 of 3

Your estimate is dated November; the notice is planned for August. What now?

  • Right. Art. 36 ust. 1.

  • Six months for works.

  • The value itself must be current.

Question 3 of 3

Sum of positions 250,000 zł; VAT 23 %. Budget with VAT, in zł?

250,000 × 1.23 = 307,500.