Theory before task 4 · 8 min

The abnormally low price: the 30 % test

Too cheap to believe?

After this lecture you can

  1. Apply both bases of art. 224 ust. 2 pkt 1 Pzp.
  2. Say which offers count in the average.
  3. Say what the authority does when an offer falls below a line.
1 / 3

Two lines, either one counts

When an offer's total price is at least 30 % below the contract value plus VAT, or below the average of the offers, the authority must ask the bidder to explain it. Only offers already rejected for set formal reasons drop out of the average; a suspicious one stays in.

Example. Estimate with VAT 500,000 zł; offers 560, 520, 480 and 300 thousand: lines at 350,000 and 326,000 zł; the 300,000 offer is below both.
Offer 1
PLN560,000
Offer 2
PLN520,000
Offer 3
PLN480,000
Offer 4
PLN300,000
2 / 3

A question, not a verdict

Falling under a line does not reject anyone. It obliges the gmina to ask, and the bidder to prove its price: methods, prices of its suppliers, its own plant. No answer by the date, or an answer that does not prove the price, means rejection.

Example. A cheap offer with a good explanation can win.
Common mistake

The net value as the base

The offer price is gross. Comparing it with 70 % of the net contract value moves the line down by a fifth and lets a suspicious offer through without a question.

Example. Gross price against value plus VAT.

The lines on another tender

Different numbers from your task.

Not to scale
The problem
  • Contract value plus VAT PLN500,000.
  • Average of the offers PLN465,000.
Step 1 of 2

Value line

70 % of the value plus VAT?

PLN500,000 × 0.70 = PLN350,000.

Step 2 of 2

Average line

70 % of the average?

PLN465,000 × 0.70 = PLN325,500.

In short. Two bases, 70 % each; below either: ask.

Check yourself

Question 1 of 3

The suspicious offer itself: in the average or out?

  • Right.

  • Only listed rejections drop out.

  • Being lowest is no ground.

Question 2 of 3

Who must prove the price is real?

  • Right. Art. 224 ust. 5.

  • The burden is on the bidder.

  • The estimator sets the lines.

Question 3 of 3

Contract value plus VAT 360,000 zł. The line, in zł?

360,000 × 0.70 = 252,000.