Theory before task 1 · 7 min

A unit price from norms: the detailed calculation

A unit price nobody has published

Course introduction

After this lecture you can

  1. Say when an investor's estimate needs a detailed calculation.
  2. Build a unit price from labour, materials and equipment.
  3. Put Kp and Z on their own bases.
1 / 3

Where an investor's price comes from

A kosztorys inwestorski is quantity × unit price, item by item, without VAT. The unit price comes first from the market: recent contracts or a current price publication. Only when nothing fits, for an unusual item or a new product, does the estimator build it from norms: hours, materials and machine time per unit, each priced. That is the detailed calculation (kalkulacja szczegółowa).

Example. A rendered reveal around a new window type has no published price: the estimator calculates it.
PLN9PLN30
  • R: labour PLN9
  • M: materials PLN30
  • S: equipment PLN2
  • Kp PLN7
  • Z PLN2
2 / 3

Each surcharge has its own base

Indirect costs (Kp) are site management, welfare and the firm's overheads; they grow with the work, so they sit on labour plus equipment. Materials already carry their purchase costs in their price. Profit (Z) sits on the base the gmina's costing assumptions name; here, labour, equipment and Kp.

Example. Labour 10 zł, equipment 2 zł, Kp 60 %: Kp is 7.20 zł, whatever the materials cost.
Common mistake

One percentage on everything

Putting Kp on materials as well inflates every material-heavy item. On an insulation slab, where materials are three quarters of the cost, the unit price jumps by half.

Example. Check the base before the rate.

A unit price for a smaller item

Different numbers from your task.

Not to scale
The problem
  • Per unit: labour PLN9.00, materials PLN30.00, equipment PLN2.00.
  • Kp 60% of R + S; Z 10% of R + S + Kp.
Step 1 of 2

Kp

Indirect costs per unit?

(PLN9.00 + PLN2.00) × 60 % = PLN6.60.

Step 2 of 2

Unit price

Unit price, net?

PLN9.00 + PLN30.00 + PLN2.00 + PLN6.60 + 10 % of (PLN9.00 + PLN2.00 + PLN6.60) = PLN49.36.

In short. R, M and S from norms; Kp on R + S; Z on its stated base; no VAT.

Check yourself

Question 1 of 3

A published price exists for the item. Does the investor still calculate it from norms?

  • Right. § 3 ust. 2.

  • Norms are the fallback, not the rule.

  • There is no such limit.

Question 2 of 3

Where do purchase costs of materials go?

  • Right. § 5 ust. 3.

  • Kp is on labour and equipment.

  • Profit is a separate surcharge.

Question 3 of 3

Labour 12 zł, equipment 3 zł per unit; Kp 70 %. Kp per unit, in zł?

(12 + 3) × 70 % = 10.50.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.