Cheat sheet
Investor's cost estimate: unit prices to award (Poland)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- Price what a contractor would charge. Norms × prices, Kp on labour and equipment, Z on those plus Kp; no VAT.
- How it is built
- Unit price = R + M + S + Kp + Z
- Usual mistake
- Kp went on the materials too. Kp sits on labour and equipment only; materials already carry their purchase costs.
- At work
- An investor's estimator prices unusual items from norms and takes the rest from current publications.
- Rule
- The tiles lie on the slope. Plan with overhangs on every edge, then ÷ cos of the pitch.
- How it is built
- Roof covering area = Plan with overhangs ÷ cos 30°
- Usual mistake
- That is the plan area, as in the przedmiar. The tiles lie on the slope: divide by cos 30°.
- At work
- The estimator checks the przedmiar's big items against the drawings before pricing them.
- Rule
- Value net, budget gross. The contract value is the sum of positions; VAT goes on once, as one markup.
- How it is built
- Contract value, net = Direct Cost
- Budget = Grand Total
- Usual mistake
- That is the budget with VAT. The contract value is net (art. 28 Pzp): read the Direct Cost.
- At work
- The estimate leaves with two figures on its cover: value net, budget with VAT, and the date.
- Rule
- 30 % below either base: ask. Gross offer against value plus VAT, and against the average of all offers.
- How it is built
- Line on value plus VAT = 0.70 × Budget with VAT
- Line on the average = 0.70 × Average offer
- Usual mistake
- That is 70 % of the net value. The test compares a gross price with the contract value plus VAT.
- At work
- On opening day the estimator gives the tender committee the two lines and the offers under them.
- Rule
- Over budget: raise it or cancel. Lowest valid gross offer minus the published gross budget.
- How it is built
- Increase = Awarded amount − Published budget
- Usual mistake
- That is measured from your estimate with VAT. The council voted a rounded budget; the gap is from that.
- At work
- The estimator gives the council the gap and the award, gross, before the session.