Investor's cost estimate: unit prices to award (Poland)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

A unit price nobody has published

Theory (7 min)
Rule
Price what a contractor would charge. Norms × prices, Kp on labour and equipment, Z on those plus Kp; no VAT.
How it is built
  • Unit price = R + M + S + Kp + Z
Usual mistake
Kp went on the materials too. Kp sits on labour and equipment only; materials already carry their purchase costs.
At work
An investor's estimator prices unusual items from norms and takes the rest from current publications.

Task 2

The roof is bigger than its plan

Theory (6 min)
Rule
The tiles lie on the slope. Plan with overhangs on every edge, then ÷ cos of the pitch.
How it is built
  • Roof covering area = Plan with overhangs ÷ cos 30°
Usual mistake
That is the plan area, as in the przedmiar. The tiles lie on the slope: divide by cos 30°.
At work
The estimator checks the przedmiar's big items against the drawings before pricing them.

Task 3

Contract value and the budget

Theory (6 min)
Rule
Value net, budget gross. The contract value is the sum of positions; VAT goes on once, as one markup.
How it is built
  • Contract value, net = Direct Cost
  • Budget = Grand Total
Usual mistake
That is the budget with VAT. The contract value is net (art. 28 Pzp): read the Direct Cost.
At work
The estimate leaves with two figures on its cover: value net, budget with VAT, and the date.

Task 4

Too cheap to believe?

Theory (8 min)
Rule
30 % below either base: ask. Gross offer against value plus VAT, and against the average of all offers.
How it is built
  • Line on value plus VAT = 0.70 × Budget with VAT
  • Line on the average = 0.70 × Average offer
Usual mistake
That is 70 % of the net value. The test compares a gross price with the contract value plus VAT.
At work
On opening day the estimator gives the tender committee the two lines and the offers under them.

Task 5

The lowest offer is over budget

Theory (7 min)
Rule
Over budget: raise it or cancel. Lowest valid gross offer minus the published gross budget.
How it is built
  • Increase = Awarded amount − Published budget
Usual mistake
That is measured from your estimate with VAT. The council voted a rounded budget; the gap is from that.
At work
The estimator gives the council the gap and the award, gross, before the session.