Course introduction · 3 min

Quantity takeoff from PDF, DWG and IFC

You are the quantity surveyor of the client's cost consultant on a six-storey mixed-use building. The tender bill goes to six bidders on Monday, and the quantities that depend on the drawings are still blank. In five tasks you measure from a PDF, a CAD file and an IFC model, apply the bill's rules, and keep waste where it belongs.

Start task 1

A concrete frame of a mid-rise building under construction, with a tower crane and blank hoardings.Fictional project
Mixed-use building, 6 storeysShops, offices and flats on a concrete frame
Works
Six storeys: shops, offices on level 1, flats on levels 2 to 5. Concrete frame.
Contract
FIDIC Red Book 2017: the Works are remeasured as built (cl. 12)
Method
Net quantities by the bill's rules; openings over 1.00 m2 out; waste in the rate
Work in the ERP
5 tasks, about 1 h 22 min

Who hands what to whom

Every arrow is a figure that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • Design teamDrawings and model
    • PDFTask 1
    • CAD fileTask 3
    • IFC modelTask 4
YouQuantity surveyor, client's cost consultant

Goes from you

    • Tender billTask 3
    BiddersSix main contractors
    • Board to orderTask 5
    Drylining buyerOrders the board

Your route through the job

One bill, from blank lines to the issue on Monday. Every task is free.

  1. Measure

    Task 1 · 10 min

    Check the scale before you measure

    You produce
    Ground slab concrete
    Document
    Tender bill
    In the ERP
    PDF Takeoff
  2. Measure

    Task 2 · 18 min

    Partitions: built height, openings out

    You produce
    Partitions
    Document
    Tender bill
    In the ERP
    PDF Takeoff
  3. Measure

    Task 3 · 20 min

    Slabs from CAD: which openings come off

    You produce
    Suspended slabs
    Document
    Tender bill
    In the ERP
    DWG Takeoff
  4. Check and use

    Task 4 · 22 min

    IFC model against the bill: the columns

    You produce
    Model reconciled
    Document
    Check sheet
    In the ERP
    BIM 3D Takeoff
  5. Check and use

    Task 5 · 12 min

    Net in the bill, waste in the rate

    You produce
    Board to order
    Document
    Order note
    In the ERP
    Bill of Quantities

From drawing to price

Each step below is one task, in the order the bill needs it.

Slab
Task 1ScaleCalibrate on a dimension.
P1
Task 2Built heightOne face, openings by size.
Slabs
Task 3Over small voidsCore out, risers in.
Frame
Task 4Model checkedName every gap.
WasteBill
Task 5Net and orderWaste in the rate.

Blue is what the task adds; grey is carried over from before.

In short. Measure what is built, by the bill's rules, from any file the designers send.