Theory before task 1 · 6 min

Scale, paper size and calibration

Check the scale before you measure

Course introduction

After this lecture you can

  1. Say why a scale is true only on the paper size it names.
  2. Calibrate a PDF on a figured dimension.
  3. Turn a measured area into a billed volume.
1 / 3

A scale is a ratio on one paper size

Designers draw a plan to fit a sheet: 1:100 on A1. Send that sheet to an A3 printer or a PDF export set to fit the page and every line shrinks by half, while the title block still says 1:100. Takeoff software that reads the scale from the drawing text trusts that label.

Example. A wall of 12 m is 120 mm on A1 at 1:100 and 60 mm on the A3 print.
12 m wall on A1, mm
USD120
Same wall on A3, mm
USD60
2 / 3

Calibrate on a figured dimension

A dimension written as a number, such as an overall 30000, is true on any print. Click its two ends and type the real length. Pick the longest one: a click error of 1 mm on a 300 mm line is 0.3 %; on a 30 mm line it is 3 %.

Example. Calibrating on a 30 m overall dimension instead of a 3 m door width cuts the error tenfold.
Common mistake

Trusting the label

The plan looks right, the numbers look plausible, and the slab comes out at a quarter of its area because lengths halved. Area errors grow with the square of the scale error. Check one known dimension before every takeoff.

Example. Measure the overall dimension once after calibrating: it must read what is printed.

Volume of another slab

Different numbers from your task.

Not to scale
The problem
  • A slab 30.0 m × 18.0 m m on an A1 sheet at 1:100, received as an A3 print.
  • Thickness 0.15 m m.
Step 1 of 2

Area

Slab area after calibrating on the 30.0 m m dimension, m2?

30.0 m × 18.0 m = 540.00 m².

Step 2 of 2

Volume

Concrete, m3?

540.00 m² × 0.15 m = 81.00 m².

In short. Calibrate on a figured dimension, then area × thickness.

Check yourself

Question 1 of 3

An A1 sheet at 1:50 is printed on A3. What is the scale on the print?

  • Right. Half the length, double the scale number.

  • Only on A1.

  • That would be a quarter of the length.

Question 2 of 3

Which dimension do you calibrate on?

  • Right.

  • It shrinks with the print, but a short bar adds click error.

  • Too short: the click error grows.

Question 3 of 3

On the A3 print of a 1:100 A1 sheet you read 40 mm. Real length, m?

40 mm × 200 = 8.00 m.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.