Length first, across the doors
Trace each partition on its centreline from end to end, through the door openings. The door comes off later as an area. A trace that stops at each door and a deduction for the same door take it off twice.
Theory before task 2 · 7 min
Partitions: built height, openings out
Trace each partition on its centreline from end to end, through the door openings. The door comes off later as an area. A trace that stops at each door and a deduction for the same door take it off twice.
Office partitions usually run past the suspended ceiling to the slab soffit, for sound and fire. The bill pays for what is built. Openings come off only above the limit stated in the bill, here 1.00 m2: a door does, a small access panel does not. National methods set other limits (NRM2 in the UK, the VOB/C trade standards in Germany); read the preamble.
From the room, a partition ends at the ceiling tiles. Measured there, the strip above the ceiling is missing on every wall of the floor, and a bidder who prices it properly looks expensive.
Different numbers from your task.
Length × height, m2?
Hint: One face.
Billed area, m2?
Hint: Doors are over 1.00 m2; panels are not.
Right.
Hidden work is paid work.
Rating changes the item, not the height.
Right.
Small openings stay in.
Size decides.
Free official texts. The lecture cites clause numbers and puts the rules in its own words.
Cl. 12.2: the method of measurement stated in the contract decides heights and deductions, not habit.
ICMS 3 places partitions with internal walls in the cost report, so the bill and the cost plan meet.
Element (partition) and work result (drylining) are two ways the same line is classified.