Theory before task 2 · 7 min

Partitions: one face, built height, openings by size

Partitions: built height, openings out

After this lecture you can

  1. Measure partitions on the centreline, end to end.
  2. Take the height the partition is built to.
  3. Deduct only openings over the bill's limit.
1 / 3

Length first, across the doors

Trace each partition on its centreline from end to end, through the door openings. The door comes off later as an area. A trace that stops at each door and a deduction for the same door take it off twice.

Example. A 10 m partition with one 0.90 m door: trace 10 m, not 9.10 m.
2 / 3

Height as built, openings by size

Office partitions usually run past the suspended ceiling to the slab soffit, for sound and fire. The bill pays for what is built. Openings come off only above the limit stated in the bill, here 1.00 m2: a door does, a small access panel does not. National methods set other limits (NRM2 in the UK, the VOB/C trade standards in Germany); read the preamble.

Example. 18 m of partition, 2.95 m clear, two doors 0.90 × 2.10: 53.10 − 3.78 = 49.32 m2.
+USD53.101−USD3.782USD49.323
  • 1 Length × height
  • 2 Doors
  • 3 Billed area
Common mistake

The height you can see

From the room, a partition ends at the ceiling tiles. Measured there, the strip above the ceiling is missing on every wall of the floor, and a bidder who prices it properly looks expensive.

Example. Read the height from the drawing note, not from the room.

Area of another partition run

Different numbers from your task.

Not to scale
The problem
  • Centreline 36.0 m m; clear height 2.95 m m to the soffit.
  • 3 doors 0.90 × 2.10 m; two access panels 0.50 × 0.50 m.
Step 1 of 2

Gross

Length × height, m2?

36.0 m × 2.95 m = 106.20 m².

Step 2 of 2

Net

Billed area, m2?

106.20 m² − 3 × 1.89 = 100.53 m²; the panels stay in.

In short. Centreline × built height, one face; openings over the limit out.

Check yourself

Question 1 of 3

A partition runs 300 mm above a suspended ceiling. Is that strip billed?

  • Right.

  • Hidden work is paid work.

  • Rating changes the item, not the height.

Question 2 of 3

An access panel of 0.40 m2 in a partition, limit 1.00 m2. Deduct it?

  • Right.

  • Small openings stay in.

  • Size decides.

Question 3 of 3

20 m of partition, 3.00 m clear, one door 1.00 × 2.10. Billed area, m2?

60.00 − 2.10 = 57.90.