Slabs from CAD: layers, labels and voids

Slabs from CAD: which openings come off

After this lecture you can

  1. Measure areas in a DWG by layer.
  2. Test each void against the bill's limit.
  3. Turn one typical slab into the concrete and formwork of all.
1 / 3

Layers do the sorting

A CAD file keeps the slab edge, the openings and the columns on separate layers. Switch off the rest and the slab is a clean outline you can measure by clicking it. Label each measurement the way the bill names it, so anyone can find it again.

Example. S-SLAB-EDGE for the outline, S-SLAB-OPNG for openings, S-COLS for columns.
2 / 3

Over small voids, out large ones

Forming a small hole costs more than the concrete it saves, so bills measure over small voids and deduct large ones. The same limit is used for the concrete and the soffit formwork. Columns are not voids: the slab is measured over them and the columns between slabs, so each joint is billed once.

Example. A 20 × 15 m slab with a 4 × 5 m stair opening and a 0.5 × 0.5 m duct: 300 − 20 = 280 m2; the duct stays in.
Stair opening, m2
USD20
Limit, m2
USD1
Duct, m2
USD0.25
Common mistake

Deducting every hole

A CAD outline with every opening subtracted looks precise. It is not the bill's quantity, and bidders price the forming of each small hole on top. Test each opening against the limit before subtracting.

Example. List the openings with their sizes first; deduct only those over the limit.

Concrete in another set of slabs

Different numbers from your task.

Not to scale
The problem
  • Slab edge 300.00 m² m2; stair opening 20.00 m² m2; two ducts of 0.25 m2.
  • 4 identical slabs, 0.20 m thick.
Step 1 of 2

Net area

Area of one slab by the rule, m2?

300.00 m² − 20.00 m² = 280.00 m².

Step 2 of 2

Concrete

Concrete in all slabs, m3?

280.00 m² × 0.20 × 4 = 224.00 m².

In short. Edge, less large openings, × thickness × number of slabs.

Check yourself

Question 1 of 3

A 0.60 × 0.60 m duct in a slab, limit 1.00 m2. Deduct it?

  • Right.

  • Size decides.

  • Same limit for both.

Question 2 of 3

Columns 500 × 500 pass through the slab. Deduct them from it?

  • Right. Columns go between slabs.

  • They are concrete, billed once.

  • Same rule on every slab.

Question 3 of 3

Slab edge 500 m2, one opening 25 m2, slab 0.25 m. Concrete in three slabs, m3?

475 × 0.25 × 3 = 356.25.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.