Theory before task 4 · 8 min

Model quantities against the bill

IFC model against the bill: the columns

After this lecture you can

  1. Group elements in a model and read a base quantity.
  2. Say why model and bill differ.
  3. Reconcile a gap to a cause before billing.
1 / 3

A model reports geometry

Base quantities in IFC are computed from the shapes the designer modelled. A column modelled from floor to floor has that length, even where it passes through a slab. The model is right about the shape and silent about the rules.

Example. A 3.50 m floor to floor with a 0.30 m slab: model column 3.50 m, bill column 3.20 m.
2 / 3

Reconcile, then bill

Group the elements, read the quantity, compare it with the bill's figure and name the cause of every difference. A gap you can explain is information; one you cannot is a risk in the tender.

Example. 20 columns 0.40 × 0.40 through 4 slabs of 0.30 m: 20 × 4 × 0.048 = 3.84 m3 of overlap.
USD90
  • Bill: between slabs USD90
  • Overlap with slabs USD10
Common mistake

Copying the model's total

The model's figure is precise and looks authoritative. Copied into the bill, it pays for the column-slab joints twice, once in each line.

Example. Every model figure in the bill needs one line saying how it was checked.

Overlap in another frame

Different numbers from your task.

Not to scale
The problem
  • 20 columns 0.40 × 0.40 m per storey, modelled floor to floor.
  • 4 suspended slabs, 0.30 m thick.
Step 1 of 2

One crossing

Concrete in one column-slab crossing, m3?

0.40 × 0.40 × 0.30 = 0.05 m².

Step 2 of 2

Gap

Model less bill, m3?

20 × 4 × 0.05 m² = 3.84 m².

In short. Model less bill = columns × slabs × section × slab thickness.

Check yourself

Question 1 of 3

A model's wall NetSideArea deducts every window. The bill keeps windows under 1 m2. Which is larger?

  • Right. It keeps the small windows.

  • The model deducted more.

  • Only if no window is under the limit.

Question 2 of 3

Where should a model figure go before the bill?

  • Right.

  • Rules first.

  • Quantities and rates are separate.

Question 3 of 3

10 columns 0.50 × 0.50, through 3 slabs of 0.20 m. Overlap, m3?

10 × 3 × 0.05 = 1.50.